Exam 3: Project Management
Exam 1: Operations and Productivity126 Questions
Exam 2: Operations Strategy in a Global Environment135 Questions
Exam 3: Project Management123 Questions
Exam 4: Forecasting144 Questions
Exam 5: Design of Goods and Services137 Questions
Exam 6: Managing Quality130 Questions
Exam 7: Statistical Process Control154 Questions
Exam 8: Process Strategy131 Questions
Exam9: Capacity and Constraint Management107 Questions
Exam 10: Location Strategies140 Questions
Exam 11: Layout Strategies161 Questions
Exam 12: Human Resources, Job Design, and Work Measurement191 Questions
Exam 13: Supply-Chain Management145 Questions
Exam 14: Outsourcing as a Supply-Chain Strategy73 Questions
Exam 15: Inventory Management155 Questions
Exam 16: Aggregate Planning134 Questions
Exam 17: Material Requirements Planning MRP and ERP169 Questions
Exam 18: Short-Term Scheduling139 Questions
Exam 19: Just-In-Time and Lean Options137 Questions
Exam 20: Maintenance and Reliability130 Questions
Exam 21: Decision-Making Tools97 Questions
Exam 22: Linear Programming100 Questions
Exam 23: Transportation Models94 Questions
Exam 24: Waiting-Line Models135 Questions
Exam 25: Learning Curves111 Questions
Exam 26: Simulation93 Questions
Select questions type
Gantt charts give a timeline for each of a project's activities, but they do not adequately illustrate the interrelationships between the activities and the resources.
(True/False)
4.8/5
(86)
Project managers have their own code of ethics, established by the Project Management Institute.
(True/False)
4.8/5
(93)
The critical path can be determined by use of either the "forward pass" or the "backward pass."
(True/False)
4.9/5
(73)
The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.
(True/False)
4.9/5
(89)
Match the following steps in Microsoft's development of Windows 7 to their respective WBS level. Step Level
Develop Windows 7 OS ?
System Testing ?
Compatible with Windows XP ?
Develop GUI's ?
Module Testing ?
(Multiple Choice)
4.9/5
(71)
A network has been crashed to the point where all activities are critical. Additional crashing
(Multiple Choice)
4.8/5
(75)
Ethical issues that may arise in projects large and small include
(Multiple Choice)
4.9/5
(88)
A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8.
(Multiple Choice)
4.9/5
(68)
Describe in words how to calculate a project's standard deviation. What assumption allows that calculation to be accurate?
(Essay)
4.9/5
(73)
One responsibility of a project manager is to make sure that the project meets its quality goals.
(True/False)
4.9/5
(85)
The __________ is the computed longest time path(s) through a network.
(Short Answer)
4.7/5
(80)
A network consists of the following list. Times are given in weeks.
Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B - 3 3 9 -- 6 10 14 , 3 5 7 4 6 11 6 8 13 , 2 4 6 3 3 9
a. Draw the network diagram.
b. Calculate the expected duration and variance of each activity.
c. Calculate the expected duration and variance of the critical path.
d. Calculate the probability that the project will be completed in less than 28 weeks.
(Essay)
4.7/5
(78)
What are the three phases of a project?
Describe each in a sentence or two.
(Essay)
4.8/5
(67)
Which of the following statements regarding PERT analysis is true?
(Multiple Choice)
4.8/5
(86)
The __________ distribution is appropriate for calculating expected activity times and activity variances in PERT networks.
(Short Answer)
4.9/5
(86)
WBS stands for which of the following project management tools?
(Multiple Choice)
4.8/5
(87)
An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is
(Multiple Choice)
4.7/5
(74)