Exam 19: Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

When work is assigned to a work center based on what is needed over time it is called which of the following?

(Multiple Choice)
4.8/5
(67)

When work is scheduled in detail using the setup and run time required for each order, then theoretically all schedules will be feasible.

(True/False)
4.7/5
(84)

Priority rules are the rules used to obtain a job sequence in production scheduling.

(True/False)
4.9/5
(76)

Assume you are sequencing jobs using Johnson's rule.A particular job requires 7 hours to assemble and then is followed by 8 hours in the painting department.Which of the following is where you would schedule this job?

(Multiple Choice)
4.9/5
(63)

Which of the following is one of the major functions of shop-floor control?

(Multiple Choice)
4.9/5
(88)

The FCFS priority rule used in sequencing production jobs will always result in a better solution than the LCFS rule.

(True/False)
5.0/5
(80)

A shop-floor control system is a system that uses data from the shop floor as well as data processing files to maintain and communicate status information on shop orders and work centers.

(True/False)
4.9/5
(85)

Which of the following is a tool of shop-floor control?

(Multiple Choice)
4.9/5
(76)

Which of the following is a principle of work center scheduling?

(Multiple Choice)
4.8/5
(83)

The objective of Johnson's rule for job sequencing is to minimize flow time from the beginning of the first job until the completion of the last job.

(True/False)
4.8/5
(76)

The LCFS and Johnson's priority rules are basically the same except LCFS uses due dates as a major determiner of job sequence.

(True/False)
4.9/5
(73)

In infinite loading no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work, nor is the actual sequence of the work as done by each resource in the work center considered.

(True/False)
4.8/5
(88)

One of the principles of work center scheduling is that once started, a job should not be interrupted.

(True/False)
4.8/5
(81)

When work is scheduled in detail using the setup and run time required for each order it is called which of the following?

(Multiple Choice)
4.8/5
(75)

When work has been scheduled in a shop that does not have sufficient resources to complete the schedule on time, the system that generated the schedule is called which of the following?

(Multiple Choice)
4.8/5
(71)

Shop-floor control (or production activity control) can involve expediting late and critical orders.

(True/False)
4.8/5
(83)

Assume you are sequencing jobs using Johnson's rule.A particular job requires 3 hours to assemble and then is followed by 2 hours in the painting department.Which of the following is where you would schedule this job?

(Multiple Choice)
4.9/5
(70)

Which of the following is not a standard measure of schedule performance which can be used to evaluate priority rules?

(Multiple Choice)
4.9/5
(77)

Which of the following is not a priority rule used to schedule the sequence of jobs in a production operation?

(Multiple Choice)
4.9/5
(79)

Shop-floor control (or production activity control) can involve reviewing the status and controlling the progress of orders as they are being worked on.

(True/False)
5.0/5
(74)