Assume you are sequencing jobs using Johnson's rule. A particular job requires 7 hours to assemble and then is followed by 8 hours in the painting department. Which of the following is where you would schedule this job?
A) As early as possible in the unfilled job sequence.
B) As late as possible in the unfilled job sequence.
C) The schedule would depend on the due date.
D) Does not matter.
E) Johnson's Rule does not apply.