Exam 18: Material Requirements Planning
Exam 1: Operations and Supply Chain Management65 Questions
Exam 2: Strategy and Sustainability63 Questions
Exam 3: Product and Service Design55 Questions
Exam 4: Strategic Capacity Management66 Questions
Exam 5: Process Analysis54 Questions
Exam 6: Production Processes46 Questions
Exam 7: Service Processes66 Questions
Exam 8: Health Care Processes60 Questions
Exam 9: Six-Sigma Quality66 Questions
Exam 10: Projects70 Questions
Exam 11: Global Sourcing and Procurement64 Questions
Exam 12: Location, Logistics and Distribution53 Questions
Exam 13: Lean and Sustainable Supply Chains70 Questions
Exam 14: Enterprise Resource Planning Systems37 Questions
Exam 15: Demand Management and Forecasting75 Questions
Exam 16: Sales and Operations Planning60 Questions
Exam 17: Inventory Control71 Questions
Exam 18: Material Requirements Planning66 Questions
Exam 19: Scheduling57 Questions
Exam 20: Constraint Management56 Questions
Select questions type
Low level coding in MRP indicates the exact status of each item managed by the system in "real time."
Free
(True/False)
4.8/5
(79)
Correct Answer:
False
Materials Requirements Planning (MRP) evolved from Enterprise Resource Planning (ERP).
Free
(True/False)
4.8/5
(87)
Correct Answer:
False
MRP stands for Material Requirements Planning.
Free
(True/False)
4.8/5
(95)
Correct Answer:
True
Which of the following files allows us to retrace a material requirement upward in the product structure through each level, identifying each parent item that created the demand?
(Multiple Choice)
4.9/5
(73)
MRP is most valuable in industries where a number of products are made in batches using the same productive equipment.
(True/False)
4.8/5
(73)
In a net change MRP system requirements and schedules are considered rigid and never updated.
(True/False)
5.0/5
(79)
The least unit cost method (LUC) lot-sizing technique calculates the order quantity by comparing the carrying cost and the setup (or ordering) costs for various lot sizes and then selects the lot in which these are most nearly equal.
(True/False)
4.8/5
(78)
Which of the following is one of the main purposes of a MRP system?
(Multiple Choice)
4.8/5
(75)
Time fences are periods of time having some specified level of opportunity for the customer to make changes.
(True/False)
4.8/5
(69)
Which of the following industry types will not benefit greatly from the application of MRP?
(Multiple Choice)
4.9/5
(83)
A master production schedule is an input to a material requirements planning (MRP) system.
(True/False)
4.8/5
(70)
In an MRP program, the program accesses the status segment of an inventory record according to specific periods called which of the following?
(Multiple Choice)
4.9/5
(86)
Which of the following is an input to the master production schedule (MPS)?
(Multiple Choice)
4.8/5
(64)
The economic order quantity (EOQ) lot sizing technique produces or acquires exactly the amount of product that is needed each time period with none carried over into future periods.
(True/False)
4.8/5
(89)
The least total cost method (LTC) lot-sizing technique calculates the order quantity by comparing the carrying cost and the setup (or ordering) costs for various lot sizes and then selects the lot in which these are most nearly equal.
(True/False)
4.9/5
(88)
An input to the material requirements planning (MRP) system is an exception report.
(True/False)
4.8/5
(92)
Computing the quantity of each component that goes into a finished product can be done by expanding (or exploding) each item in a product structure file and summing at all levels.
(True/False)
4.8/5
(68)
Which of the following industry types has high expected benefits from the application of MRP?
(Multiple Choice)
4.9/5
(82)