What options do project managers have to alleviate resource problems? Briefly describe each method.

(Short Answer)
4.7/5
(76)

________ is an attempt to reduce the peaks and valleys in resource needs by shifting the schedules of conflicting activities within their earliest and latest start dates.

(Short Answer)
4.8/5
(72)

Projects cannot have more than one critical path.

(True/False)
4.8/5
(76)

Explain what the close out phase of the project life cycle involves.

(Essay)
4.8/5
(82)

Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?

(Multiple Choice)
4.9/5
(87)

In a network diagram, an "activity"

(Multiple Choice)
4.9/5
(80)

Describe the four steps followed to determine the minimum- cost schedule for a project that is planned based on the critical path method (CPM).

(Essay)
4.7/5
(75)

The ________ cost refers to the additional cost associated with reducing an activity time in a project network.

(Short Answer)
4.9/5
(87)

Risk is a measure of the probability and consequences of not reaching a defined project goal.

(True/False)
5.0/5
(87)

Describe four stages of development process.

(Essay)
4.8/5
(81)

If one activity along the critical path is delayed, the entire project will be delayed.

(True/False)
4.9/5
(66)

________ is the shortest time in which an activity can be completed, if all goes exceptionally well.

(Essay)
4.9/5
(84)

To calculate the probability of completing a project by a certain date,

(Multiple Choice)
4.8/5
(73)

Why do managers want to know the slack of activities?

(Short Answer)
4.8/5
(66)

Assuming a beta distribution is being used, if the most optimistic time for an activity decreases by 12 days, what will happen to the expected time for that activity?

(Multiple Choice)
4.9/5
(85)

In monitoring a project, negative slack indicates how much an activity has been pushed beyond its planned latest start dates.

(True/False)
5.0/5
(86)

Why is knowing the critical path in a project important?

(Short Answer)
4.9/5
(73)

All activities on the critical path must be crashed, or expedited, in order to reduce the overall project completion time.

(True/False)
4.9/5
(72)

If a project has multiple critical paths, which of the following variances should be used in analyzing project completion time probabilities?

(Multiple Choice)
4.9/5
(74)

When using the beta distribution for estimating activity times,

(Multiple Choice)
4.7/5
(77)