Exam 3: Developing Project Proposals
Exam 1: Project Management Concepts99 Questions
Exam 2: Identifying and Selecting Projects92 Questions
Exam 3: Developing Project Proposals153 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence166 Questions
Exam 5: Developing the Schedule127 Questions
Exam 6: Resource Utilization45 Questions
Exam 7: Determining Costs, Budget and Earned Value103 Questions
Exam 8: Managing Risk72 Questions
Exam 9: Closing the Project64 Questions
Exam 10: The Project Manager165 Questions
Exam 11: The Project Team275 Questions
Exam 12: Project Communication and Documentation164 Questions
Exam 13: Project Management Organizational Structures109 Questions
Select questions type
The contractor must notify the customer immediately of any actual or anticipated cost savings or schedule delays.
(True/False)
4.9/5
(89)
The objective of the cost section of the contractor proposal is to convince the customer that the contractor's price for the proposed project is realistic and reasonable.
(True/False)
4.9/5
(78)
Proposals that promise too much or are overly optimistic may seem believable and support that the contractor understands what needs to be done and how to do it.
(True/False)
4.8/5
(80)
A(n)____ lists the major project tasks and the name of the person, organization, or subcontractor responsible for the achievement of each task.
(Multiple Choice)
4.8/5
(77)
Contractors may outsource some of the work to subcontractors or consultants to perform certain project tasks.
(True/False)
4.8/5
(65)
A contractor should bid on RFPs where there is little or no competition and avoid ones where they might have a competitor bid on the project.
(True/False)
4.9/5
(77)
One party is prohibited from disclosing confidential information, technologies, or processes utilized by the other party during the project to anyone else or using it for any purpose other than work on the project.
(True/False)
4.8/5
(80)
Cost-reimbursement contracts are most appropriate for projects that
(Multiple Choice)
4.9/5
(85)
As soon as a contractor finds out it is the winner, it can start working on the project.
(True/False)
4.8/5
(73)
____ outlines the circumstances under which the contractor must notify the customer immediately of any actual or anticipated schedule delays.
(Multiple Choice)
4.8/5
(79)
Responding to follow-up communications may be viewed as an unfair advantage for contractors.
(True/False)
4.9/5
(79)
Helping customers identify needs, even if they are needs your company cannot help them address, is a way to position your company to win future contracts.
(True/False)
4.8/5
(80)
After submitting a proposal to a customer, if no limitations for contact were stated in the RFP then the contractor should
(Multiple Choice)
4.8/5
(77)
The length of the proposal is not as important as the quality of the information contained in the proposal.
(True/False)
4.9/5
(72)
The costs associated with the preparation of a proposal are
(Multiple Choice)
4.8/5
(83)
Fixed-price contracts are most appropriate for projects that
(Multiple Choice)
4.9/5
(57)
Materials are typically part of the ____ section of a proposal.
(Multiple Choice)
4.8/5
(77)
Many contracts include the ____, which states that the customer will make the final payment at the completion of the project.
(Multiple Choice)
4.8/5
(72)
A specific proposed solution should be suggested for the customer's need.
(True/False)
4.8/5
(83)
Showing 61 - 80 of 153
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)