Exam 8: Managing Risk

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Risks ____ should be given higher priority because if the risk occurs, it would have a greater impact on the schedule than if it was associated with activities on a path that has a large positive value of total slack.

Free
(Multiple Choice)
4.8/5
(81)
Correct Answer:
Verified

C

Track and document which risks ____ and the impact of those risks.

Free
(Multiple Choice)
4.9/5
(85)
Correct Answer:
Verified

D

A risk is

Free
(Multiple Choice)
4.9/5
(84)
Correct Answer:
Verified

A

If the risks seem ____, the contractor may decide to not bid on a proposed project.

(Multiple Choice)
4.9/5
(86)

The most common method of identifying the sources of risks is:

(Multiple Choice)
4.7/5
(86)

____ can be to avoid the risk, mitigate the risk, or accept the risk.

(Multiple Choice)
4.8/5
(84)

The possible impact for rain or snow on the day of an event is

(Multiple Choice)
4.8/5
(67)

____ is a rating of low, medium, or high based upon the expected probability of a risk occurring during the project.

(Multiple Choice)
4.9/5
(79)

Establishing risk categories may help to identify and evaluate risks.Some categories to help identify risks include all the following except:

(Multiple Choice)
4.9/5
(82)

Risks may change as the project progresses and should be reflected in

(Multiple Choice)
4.9/5
(66)

____ includes taking action to prevent or minimize the likelihood of occurrence or the impact of such unfavorable events.

(Multiple Choice)
4.8/5
(79)

The possible response plan for vendor delay in delivery of critical equipment is

(Multiple Choice)
4.8/5
(76)

____ is a rating of low, medium, or high based on the expected level of change in completing the project's objective if the risk were to occur during the project.

(Multiple Choice)
4.9/5
(84)

Waiting for unfavorable events to occur and then reacting to them

(Multiple Choice)
4.9/5
(84)

Some level of risk planning should be done during ____ of the project life cycle to make sure that a contractor understands the risks involved with bidding on a proposed project.With knowledge of potential risks, the contractor can include contingency or management reserve amounts in the bid price.

(Multiple Choice)
4.9/5
(74)

The project team should not change the estimated impacts of previously identified risks as the project progresses.

(True/False)
4.8/5
(84)

Waiting for problematic events to occur and then reacting to them can result in panic and costly responses.

(True/False)
5.0/5
(69)

Regularly review and evaluate ____ to determine if there are any changes to the likelihood of occurrence or the potential impact of any of the risks.

(Multiple Choice)
5.0/5
(76)

Addressing risks proactively will increase the chances of accomplishing the project objective.

(True/False)
4.7/5
(73)

Historical information from past projects is another source that can be helpful in identifying possible risks.

(True/False)
4.8/5
(81)
Showing 1 - 20 of 72