Waiting to develop a proposal until an RFP is announced is important to be sure all the information is available.

(True/False)
4.9/5
(86)

Quantitative and qualitative benefits to the customer should be stated to help convince the customer of the value of the proposed result.

(True/False)
4.8/5
(83)

By having a customer supply schedule, the contractor is protected from incurring schedule slippage caused by customer delays in furnishing information, parts, or other items.

(True/False)
4.9/5
(92)

Contacts with potential clients

(Multiple Choice)
4.9/5
(79)

The cost section of the proposal is to convince the customer that the contractor

(Multiple Choice)
4.7/5
(67)

The objective of the ____ section of the contractor proposal is to convince the customer that the contractor can do the proposed work (the project)and achieve the intended results.

(Multiple Choice)
4.8/5
(81)

The customer selects the proposal that it expects will provide the best value.

(True/False)
4.7/5
(75)

The amount of profit on a project is adjusted depending upon the amount of competition for a project.

(True/False)
5.0/5
(74)

It is unethical to submit an unsolicited proposal to a customer.

(True/False)
4.8/5
(81)

____ is an amount that the contractor will usually add on costs estimated for labor, materials, subcontractors and consultants, equipment and facilities, travel and documentation.

(Multiple Choice)
4.9/5
(78)

Relationship building necessitates being a good listener and

(Multiple Choice)
5.0/5
(84)

Realistic estimated hours and hourly labor rate for each person or classification is included in the cost section.

(True/False)
4.9/5
(64)

Submitting a proposal that meets the customer's statement of work and requirements is all that is needed to secure a contract.

(True/False)
4.8/5
(82)

____ is the percent of the number of proposals a contractor won out of the total number of proposals the contractor submitted to various customers over a particular time period.

(Multiple Choice)
4.9/5
(76)

In a contract's terms of payment, ____ are based on the expected overall duration of the project schedule.

(Multiple Choice)
4.9/5
(76)

Specific criteria listed in the RFP should be restated in the proposal to reinforce to the customer that the contractor understands the requirements.

(True/False)
4.9/5
(88)

Build credibility based on

(Multiple Choice)
4.8/5
(65)

The win ratio approach for calculating the win ratio gives

(Multiple Choice)
4.8/5
(74)

Documentation deliverables are sometimes shown as separate costs in the project cost estimate.

(True/False)
4.7/5
(91)

It is ok to use foul language, slang, and jargon with clients.Especially when they are using them.

(True/False)
4.8/5
(72)