Exam 2: Project Management
Exam 1: Using Operations to Compete107 Questions
Exam 2: Project Management151 Questions
Exam 3: Process Strategy149 Questions
Exam 4: Process Analysis192 Questions
Exam 5: Quality and Performance223 Questions
Exam 6: Capacity Planning133 Questions
Exam 7: Constraint Management160 Questions
Exam 8: Lean Systems179 Questions
Exam 9: Supply Chain Inventory Management216 Questions
Exam 10: Supply Chain Design93 Questions
Exam 11: Supply Chain Location Decisions126 Questions
Exam 12: Supply Chain Integration130 Questions
Exam 13: Supply Chain Sustainability and Humanitarian Logistics77 Questions
Exam 14: Forecasting183 Questions
Exam 15: Operations Planning and Scheduling191 Questions
Exam 16: Resource Planning149 Questions
Exam 17: Decision Making118 Questions
Exam 18: Waiting Line127 Questions
Exam 19: Special Inventory Models53 Questions
Exam 20: Linear Programming84 Questions
Exam 21: Simulation61 Questions
Exam 22: Financial Analysis60 Questions
Exam 23: Acceptance Sampling Plans88 Questions
Exam 24: Measuring Output Rates103 Questions
Exam 25: Learning Curve Analysis56 Questions
Exam 26: Operations Scheduling131 Questions
Select questions type
Table 2.4
-Using Table 2.4,what is the early start time for activity D?
(Multiple Choice)
4.9/5
(82)
Table 2.12
-Using Table 2.12,if the project's normal earliest completion time is to be reduced by two weeks,what is the minimum additional cost that will be incurred in achieving this two-week reduction?
(Multiple Choice)
4.8/5
(82)
Table 2.2
-Using Table 2.2,if the expected times for activities A,G,and H increased by 2,3,and 4 weeks,respectively,by how many weeks would the project's earliest expected time of completion increase?
(Multiple Choice)
4.9/5
(82)
You are given the following information about activity A:
What will it cost to complete activity A in 8 weeks?
(Multiple Choice)
4.9/5
(95)
A risk-management plan contains all identified risks to a project plus the ways that they can be circumvented.
(True/False)
4.8/5
(82)
A(n)________ is an interrelated set of activities that has a definite starting and ending point and that results in a unique outcome for a specific allocation of resources.
(Essay)
4.9/5
(71)
Table 2.3
-Using Table 2.3,if the project is due to be completed in 28 days,what is the probability that the project will be completed on or before the due date?
(Multiple Choice)
4.8/5
(87)
A project manager should stop crashing a project if the time budget has been met or if the crash costs have exceeded the savings in indirect and penalty costs.
(True/False)
4.9/5
(78)
Figure to accompany Table 2.1
Table 2.1
-Using the information shown in Table 2.1,what is the earliest finish time for activity A?
(Multiple Choice)
4.8/5
(69)
A project is an interrelated set of activities that has a definite starting and ending point.
(True/False)
4.8/5
(73)
A project has three paths.A-B-C has a length of 25 days.A-D-C has a length of 15 days.Finally,A-E-C has a length of 20 days.Which one of the following statements is TRUE?
(Multiple Choice)
4.8/5
(76)
What characteristics should be considered when selecting project team members? Briefly describe these characteristics for members of a project team assigned to improve a teller's job in a bank.
(Essay)
4.9/5
(82)
Figure to accompany Table 2.9
Table 2.9
-What is the crashing cost per week for activity F in Table 2.9?
(Multiple Choice)
4.8/5
(78)
Table 2.11
-Using Table 2.11 and assuming all activities except D,F,H,and K are available to be crashed,what is the minimum cost to be incurred in reducing the total project earliest completion time by one week?
(Multiple Choice)
4.9/5
(74)
The phase of project management that takes the most resources is the execution phase.
(True/False)
4.9/5
(89)
The optimistic time is the probable time required to perform the activity.
(True/False)
4.7/5
(95)
Which one of the following statements regarding Figure 2.2 is TRUE?
A)Activity S cannot finish until activity T finishes.
B)Activity T cannot begin until activity U is completed.
C)Activity U cannot begin until activities S and T have been completed.
D)Activity V cannot begin until activity S has been completed.
Answer: C
Reference: Planning Projects
Difficulty: Moderate
Keywords: activity precedence
-If a project has exactly one critical path,which one of the following statements is TRUE?