Exam 2: Project Management
Exam 1: Using Operations to Compete107 Questions
Exam 2: Project Management151 Questions
Exam 3: Process Strategy149 Questions
Exam 4: Process Analysis192 Questions
Exam 5: Quality and Performance223 Questions
Exam 6: Capacity Planning133 Questions
Exam 7: Constraint Management160 Questions
Exam 8: Lean Systems179 Questions
Exam 9: Supply Chain Inventory Management216 Questions
Exam 10: Supply Chain Design93 Questions
Exam 11: Supply Chain Location Decisions126 Questions
Exam 12: Supply Chain Integration130 Questions
Exam 13: Supply Chain Sustainability and Humanitarian Logistics77 Questions
Exam 14: Forecasting183 Questions
Exam 15: Operations Planning and Scheduling191 Questions
Exam 16: Resource Planning149 Questions
Exam 17: Decision Making118 Questions
Exam 18: Waiting Line127 Questions
Exam 19: Special Inventory Models53 Questions
Exam 20: Linear Programming84 Questions
Exam 21: Simulation61 Questions
Exam 22: Financial Analysis60 Questions
Exam 23: Acceptance Sampling Plans88 Questions
Exam 24: Measuring Output Rates103 Questions
Exam 25: Learning Curve Analysis56 Questions
Exam 26: Operations Scheduling131 Questions
Select questions type
Table 2.3
-Using Table 2.3,what is the earliest expected time of completion of the whole project?
(Multiple Choice)
4.9/5
(85)
Table 2.4
-Using Table 2.4,what is the minimum number of activities that would have to be crashed to cause a decrease in the project's earliest completion date?
(Multiple Choice)
4.9/5
(78)
If the sum of the variances on the critical path (and all other network paths)is equal to zero,what is the probability that the project will be completed by its earliest expected completion date?
(Multiple Choice)
4.9/5
(71)
Table 2.3
-Using Table 2.3,if the project manager wants at least a 98% probability that the project will be completed on or before the due date,what is the shortest project due date that will satisfy the manager?
(Multiple Choice)
4.9/5
(86)
Draw the network corresponding to the following information.Also,complete the table,identify the critical path,and specify project completion time.

(Essay)
4.7/5
(92)
Assume that activity G has the following times: Early start time = 7 days
Early finish time = 13 days
Late start time = 15 days
Late finish time = 21 days
Which of the following statements is TRUE about activity G?
(Multiple Choice)
4.9/5
(87)
Table 2.16
Four possible options exist to crash activities: crash A by one week at a cost of $6,000;crash C by two weeks at a cost of $15,000;crash E by one week at a cost of $2,000;and crash I one week at a cost of $7,000.What is the maximum amount of additional profit that can be made by crashing an option (or options)?
A)less than or equal to $4,000
B)greater than $4000 but less than or equal to $8,000
C)greater than $8000 but less than or equal to $12,000
D)greater than $12,000
Answer: B
Reference: Planning Projects
Difficulty: Moderate
Keywords: activity crashing,project completion
AACSB: Analytic skills
-A good risk management plan will contain which of these elements?
(Multiple Choice)
4.8/5
(83)
Table 2.5
-Using Table 2.5,what is the variance for activity F?
(Multiple Choice)
5.0/5
(76)
The following table contains a list of activities,with early- and late-start and finish times and crash costs for the network shown in the figure.All start and finish times and crash costs are on a per-week basis.Each activity can be reduced by one week at the most.
a.Determine the uncrashed activity lengths for activities A though K.
b.Determine the minimum completion cost for this project if each week carries a fixed cost of $1,000.

(Essay)
4.8/5
(61)
Table 2.5
-Using Table 2.5,what is the latest finish time for activity D?
(Multiple Choice)
5.0/5
(83)
In an activity-on-node [AON] network,the nodes represent ________,whereas the arcs represent ________.
(Multiple Choice)
4.8/5
(93)
The work breakdown structure is a statement of all work that has to be completed.
(True/False)
4.8/5
(67)
Heidi was part of a project team that retained their roles within the organization and was on loan to the project due to her technical expertise.In effect,she reported to two bosses,one in her functional area and also to the project manager.Heidi is operating within a(n)________ organizational structure.
(Essay)
5.0/5
(89)
The phase of project management that takes the most resources is the ________,during which managers focus on activities that pertain to deliverables.
(Essay)
4.9/5
(87)
Table 2.14
You are responsible for managing a project with the following activities (times are given in weeks).
-Using Table 2.14,what is the probability that the project will take 16 or more weeks to complete?
(Multiple Choice)
4.9/5
(63)
Figure to accompany Table 2.9
Table 2.9
-What is the crashing cost per week for activity E in Table 2.9?
(Multiple Choice)
4.8/5
(80)
Figure to accompany Table 2.9
Table 2.9
-If a decision is made to crash activity D in Table 2.9 by one week,what is the cost for this one week of crashing?
(Multiple Choice)
4.8/5
(74)
Table 2.12
-Using Table 2.12,what is the minimum time schedule for this project?
(Multiple Choice)
4.8/5
(75)
Table 2.14
You are responsible for managing a project with the following activities (times are given in weeks).
-Using Table 2.14,what is the critical path and expected completion time for this project?
(Multiple Choice)
4.7/5
(79)