Exam 3: Project Management
Exam 1: Operations and Productivity129 Questions
Exam 2: Operations Strategy in a Global Environment120 Questions
Exam 3: Project Management124 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services121 Questions
Exam 6: Managing Quality125 Questions
Exam 7: Process Strategy113 Questions
Exam 8: Location Strategies121 Questions
Exam 9: Layout Strategies146 Questions
Exam 10: Human Resources,job Design,and Work Measurement159 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management165 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand ERP113 Questions
Exam 15: Short-Term Scheduling116 Questions
Exam 16: Lean Operations116 Questions
Exam 17: Maintenance and Reliability114 Questions
Exam 18: Sustainability in the Supply Chain84 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management101 Questions
Exam 21: Supply Chain Management Analytics67 Questions
Exam 22: Decision-Making Tools100 Questions
Exam 23: Linear Programming98 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation75 Questions
Select questions type
A network consists of the activities in the following list.Times are given in weeks.
a.Draw the network diagram.
b.Calculate the ES,EF,LS,LF,and Slack for each activity.
c.What is project completion time?
(Essay)
4.8/5
(76)
Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. 
(Multiple Choice)
4.8/5
(84)
A project manager is interested in crashing a project with variable activity times.Which of the following tools should he/she employ?
(Multiple Choice)
4.9/5
(83)
Which of the following is NOT one of the phases of project management?
(Multiple Choice)
4.9/5
(75)
The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.
(True/False)
4.8/5
(81)
The ES of an activity that has only one predecessor is simply the EF of that predecessor.
(True/False)
4.7/5
(73)
If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000,what is the crash cost per period?
(Multiple Choice)
4.8/5
(79)
Project managers have their own code of ethics,established by the Project Management Institute.
(True/False)
4.9/5
(87)
The expected activity time in PERT analysis is calculated as:
(Multiple Choice)
4.8/5
(70)
Ill-defined projects are typified by software development and new technology.
(True/False)
4.8/5
(88)
Which of the following statements regarding PERT times is true?
(Multiple Choice)
4.8/5
(76)
How is the expected completion time of a project activity,and of a PERT project,computed?
(Essay)
4.8/5
(77)
Work breakdown structure is a useful tool in project management because it addresses the timing of individual work elements.
(True/False)
4.7/5
(81)
An activity on a PERT network has these time estimates: optimistic = 1,most likely = 2,and pessimistic = 5.What is its expected activity time?
(Multiple Choice)
4.7/5
(89)
The project organization works best when which of the following conditions are satisfied? I.Work tasks can be defined with a specific goal and deadline.
II.The job is typical and familiar to the existing organization.
III.The work contains interrelated tasks requiring specialized skills.
IV.The project is temporary but unimportant to long-term organizational success.
V.The project cuts across organizational lines.
(Multiple Choice)
4.8/5
(81)
One responsibility of a project manager is to make sure that the project meets its quality goals.
(True/False)
4.8/5
(78)
The ________ has established a code of ethics especially for project managers.
(Essay)
4.8/5
(75)
Showing 81 - 100 of 124