Describe in words how to calculate a project's standard deviation.What assumption allows that calculation to be accurate?

(Essay)
4.8/5
(84)

Identify several advantages of using PERT (and CPM).

(Essay)
4.8/5
(90)

The ________ distribution is appropriate for calculating expected activity times and activity variances in PERT networks.

(Essay)
4.9/5
(73)

What are the three phases of a project? Describe each in a sentence or two.

(Essay)
4.9/5
(94)

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

(Multiple Choice)
4.8/5
(91)

Which of the following statements regarding time-cost tradeoffs in CPM networks is false?

(Multiple Choice)
4.8/5
(97)

Describe the differences between a Gantt chart and a PERT/CPM network.

(Essay)
4.7/5
(82)

In project management,crashing an activity must consider the impact on all paths in the network.

(True/False)
4.9/5
(71)

What is the basic difference between PERT and CPM?

(Essay)
4.9/5
(68)

Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project.Given the project table below calculate the crash cost for 8 hours of time-savings.Suppose Pirmin calls the customer and asks for a project extension,reducing the amount of time he needs to crash.Calculate both the maximum time-savings available on a $25 crash budget and the cost to crash four hours of savings. Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project.Given the project table below calculate the crash cost for 8 hours of time-savings.Suppose Pirmin calls the customer and asks for a project extension,reducing the amount of time he needs to crash.Calculate both the maximum time-savings available on a $25 crash budget and the cost to crash four hours of savings.

(Essay)
4.9/5
(79)

A simple CPM network has three activities,A,B,and C.A is an immediate predecessor of B and of C.B is an immediate predecessor of C.The activity durations are A=4,B=3,C=8.

(Multiple Choice)
4.8/5
(75)

A code of ethics especially for project managers:

(Multiple Choice)
4.9/5
(78)

The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates.

(True/False)
4.9/5
(59)

Ethical issues that can arise in projects include gifts from contractors,pressure to mask delays with false status reports,and pressure to compromise project quality to meet bonuses or avoid penalties related to schedules.

(True/False)
5.0/5
(57)

Which of the following statements regarding critical paths is true?

(Multiple Choice)
4.9/5
(70)

Shortening the project's duration by deleting unnecessary activities is called "project crashing."

(True/False)
4.8/5
(88)

The beta distribution is used in project management to:

(Multiple Choice)
4.9/5
(69)

Contract requirements state that a project must be completed within 180 working days,or it will incur penalties for late completion.Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400.What is the probability that the project will be completed before the late-payment deadline?

(Multiple Choice)
4.9/5
(78)

The network analysis method that allows activity times to vary is ________.

(Essay)
4.9/5
(72)

A network consists of the following list.Times are given in weeks. A network consists of the following list.Times are given in weeks.    a.Draw the network diagram. b.Which activities form the critical path? c.How much slack exists at activities A and F? d.What is the duration of the critical path? a.Draw the network diagram. b.Which activities form the critical path? c.How much slack exists at activities A and F? d.What is the duration of the critical path?

(Essay)
4.9/5
(82)