Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A combination of effective Gantt chart use and other tactics allowed Delta to cut the average time for a plane layover by what % of the original 60 minute duration?

(Multiple Choice)
4.7/5
(79)

Which of the following statements regarding Bechtel is true?

(Multiple Choice)
4.9/5
(76)

Which of the following statements about Bechtel is true?

(Multiple Choice)
4.8/5
(77)

The control of projects involves close monitoring of which of the following?

(Multiple Choice)
4.9/5
(78)

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.

(Multiple Choice)
4.8/5
(79)

Explain why the critical path is the longest,not the shortest,path through a network.

(Essay)
5.0/5
(92)

The phases of project management are:

(Multiple Choice)
4.8/5
(85)

Consider the network described in the table below. Consider the network described in the table below.    a.Calculate the expected duration of each activity. b.Calculate the expected duration and variance of the critical path. c.Calculate the probability that the project will be completed in fewer than 30 time units. a.Calculate the expected duration of each activity. b.Calculate the expected duration and variance of the critical path. c.Calculate the probability that the project will be completed in fewer than 30 time units.

(Essay)
4.7/5
(75)

The shortest of all paths through the network is the critical path.

(True/False)
4.9/5
(89)

A(n)________ is an organization formed to ensure that programs (projects)receive the proper management and attention.

(Essay)
4.9/5
(85)

In a PERT network,non-critical activities that have little slack need to be monitored closely:

(Multiple Choice)
4.9/5
(74)

The critical path for the network activities shown below is ________ with duration ________. The critical path for the network activities shown below is ________ with duration ________.

(Multiple Choice)
4.8/5
(84)

A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

(Multiple Choice)
4.8/5
(88)

A project organization:

(Multiple Choice)
4.9/5
(79)

What are the earliest activity start time and latest activity start time,and how are they computed?

(Essay)
4.9/5
(85)

The main difference between PERT and CPM is that:

(Multiple Choice)
4.8/5
(86)

A project being analyzed by PERT has 38 activities,16 of which are on the critical path.If the estimated time along the critical path is 90 days with a project variance of 25,what is the probability that the project will be completed in 88 days or less?

(Multiple Choice)
4.8/5
(72)

Which of the following statements regarding PERT analysis is true?

(Multiple Choice)
4.9/5
(97)

Which of these statements regarding time-cost tradeoffs in CPM networks is true?

(Multiple Choice)
4.8/5
(84)

PERT calculations typically include the duration variance of each activity.What is the purpose of this calculation,i.e.what's the role of variances in PERT analysis?

(Essay)