Exam 3: Project Management
Exam 1: Operations and Productivity129 Questions
Exam 2: Operations Strategy in a Global Environment120 Questions
Exam 3: Project Management124 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services121 Questions
Exam 6: Managing Quality125 Questions
Exam 7: Process Strategy113 Questions
Exam 8: Location Strategies121 Questions
Exam 9: Layout Strategies146 Questions
Exam 10: Human Resources,job Design,and Work Measurement159 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management165 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand ERP113 Questions
Exam 15: Short-Term Scheduling116 Questions
Exam 16: Lean Operations116 Questions
Exam 17: Maintenance and Reliability114 Questions
Exam 18: Sustainability in the Supply Chain84 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management101 Questions
Exam 21: Supply Chain Management Analytics67 Questions
Exam 22: Decision-Making Tools100 Questions
Exam 23: Linear Programming98 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation75 Questions
Select questions type
Project management at the Tour de France races can be complex because:
(Multiple Choice)
4.7/5
(69)
The critical path can be determined by use of either the "forward pass" or the "backward pass."
(True/False)
5.0/5
(78)
The ________ distribution is used by PERT analysis to calculate expected activity times and variances.
(Multiple Choice)
4.9/5
(79)
A(n)________ divides a project into more and more detailed components.
(Essay)
4.9/5
(91)
Which of the following statements concerning CPM activities is false?
(Multiple Choice)
5.0/5
(66)
Which of the following statements regarding PERT times is true?
(Multiple Choice)
4.9/5
(71)
A network has been crashed to the point where all activities are critical.Additional crashing:
(Multiple Choice)
4.8/5
(80)
The time an activity will take assuming very unfavorable conditions is:
(Multiple Choice)
4.9/5
(79)
A project being analyzed by PERT has 60 activities,13 of which are on the critical path.If the estimated time along the critical path is 214 days with a project variance of 100,what is the probability that the project will take 224 days or more to complete?
(Multiple Choice)
4.9/5
(67)
A simple CPM network has three activities,D,E,and F.D is an immediate predecessor of E and of F.E is an immediate predecessor of F.The activity durations are D=4,E=3,F=8.
(Multiple Choice)
4.8/5
(81)
WBS stands for which of the following project management tools?
(Multiple Choice)
4.8/5
(93)
Ethical issues that may arise in projects large and small include:
(Multiple Choice)
4.8/5
(83)
Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64.There is a .90 probability that the project will be completed before approximately day:
(Multiple Choice)
4.9/5
(83)
A PERT project has 45 activities,19 of which are on the critical path.The estimated time for the critical path is 120 days.The sum of all activity variances is 64,while the sum of variances along the critical path is 36.What is the probability that the project can be completed between days 108 and 120?
(Multiple Choice)
4.9/5
(93)
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for each of the three activities?
b.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
c.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
(Essay)
4.8/5
(66)
Activity D on a CPM network has predecessors B and C,and has successor F.D has duration 6.B's earliest finish is 18,while C's is 20.F's late start is 26.Which of the following is definitely true?
(Multiple Choice)
4.8/5
(77)
The ________ is a project management technique using only one time factor per activity that enables managers to schedule,monitor,and control large and complex projects.
(Essay)
4.8/5
(76)