Exam 13: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project. The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.    Table ZZ -Using Table ZZ,the earliest start (ES)time for activity D is Table ZZ -Using Table ZZ,the earliest start (ES)time for activity D is

(Multiple Choice)
4.9/5
(78)

In general,the earliest finish time for an activity is equal to

(Multiple Choice)
4.9/5
(75)

Which of the following statements is generally true regarding the relationship between project crashing costs and indirect costs?

(Multiple Choice)
4.9/5
(76)

One disadvantage of Gantt charts,especially for large projects,is that it does not

(Multiple Choice)
4.8/5
(77)

Issues of cultural diversity in project management should only be addressed if and when they arise.

(True/False)
4.9/5
(86)

The estimated variance for an activity with a most likely time (m)equal to 11 days,the optimistic time (a)equal to 6 days,and the pessimistic time (b)equal to 18 days is

(Multiple Choice)
4.9/5
(83)

Control,one of the basic elements of a project plan,involves a set of procedures for monitoring and evaluating progress and performance.

(True/False)
4.8/5
(79)

The three primary elements of project management include planning,scheduling,and costing.

(True/False)
4.8/5
(80)

A project consists of the following activities: A project consists of the following activities:    Table XX -Using Table XX,the critical path for this project consists of activities Table XX -Using Table XX,the critical path for this project consists of activities

(Multiple Choice)
4.9/5
(78)

Indirect costs always increase as a project's duration increases.

(True/False)
4.9/5
(87)

What is a scope statement?

(Essay)
4.8/5
(88)

The reduction in one or more activities normal time to shorten the project duration is called

(Multiple Choice)
4.9/5
(82)

A project consists of the following four activities with activity times in days: A project consists of the following four activities with activity times in days:    Table CC -Using table CC,what is the total allowable crash time for activity B? Table CC -Using table CC,what is the total allowable crash time for activity B?

(Multiple Choice)
4.8/5
(73)

A dummy variable is an activity inserted into the AOA network diagram to show a precedence relationship,but does not represent any passage of time.

(True/False)
4.8/5
(85)

In project management the term slack refers to the amount of time

(Multiple Choice)
4.9/5
(86)

A unique,one-time operational activity or effort is referred to as a process.

(True/False)
4.9/5
(77)

The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project. The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.    Table ZZ -Using Table ZZ,the critical path for the project consists of activities Table ZZ -Using Table ZZ,the critical path for the project consists of activities

(Multiple Choice)
4.9/5
(73)

The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project. The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.    Table ZZ -Using Table ZZ,the probability that the project could be completed in 34 weeks or less is approximately Table ZZ -Using Table ZZ,the probability that the project could be completed in 34 weeks or less is approximately

(Multiple Choice)
4.9/5
(80)

Crashing activities with positive slack reduces a project's duration.

(True/False)
4.8/5
(80)

Briefly discuss project management and what it involves.

(Essay)
4.9/5
(89)
Showing 61 - 80 of 98