Exam 11: Standard Costs for Control: Flexible Budgets and Manufacturing Overhead

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Flexible budgets only reflect changes in the volume of activity in the variable overhead estimates.

(True/False)
4.8/5
(79)

ABB works in the reverse way to ABC as under ABB, once the sales volume and production volume have been estimated then the demand for activities can be determined.

(True/False)
4.8/5
(85)

Assume the number of machine hours is the cost driver for variable overhead. The difference between the actual variable overhead and the flexible budget for variable overhead (based on standard machine hours allowed for actual output) is the

(Multiple Choice)
4.8/5
(87)

Bozo Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year: Bozo Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year:   Calculate the total standard overhead rate per direct labour hour (variable and fixed). Calculate the total standard overhead rate per direct labour hour (variable and fixed).

(Multiple Choice)
4.8/5
(80)

When a flexible budget is used, a decrease in the actual production level within a range of activity would

(Multiple Choice)
4.8/5
(78)

Overhead cost performance report Explain how a manager can use an overhead cost performance report to investigate the underlying causes of significant overhead variances.

(Essay)
4.9/5
(76)

In the accounting recording system, unfavourable variances are recorded in a similar way to revenue and favourable variances are recorded in a similar way to expenses.

(True/False)
4.8/5
(70)

Which of the following criticisms of standard costing systems is false?

(Multiple Choice)
4.8/5
(80)

When calculating the predetermined manufacturing overhead rates using direct labour hours as the cost driver the formula is 'total overhead divided by total direct labour hours'. This rate is applied to both the variable overhead and the fixed overhead.

(True/False)
4.8/5
(77)

Carvelle Cabinets set the following standard cost per unit for 2008. Carvelle Cabinets set the following standard cost per unit for 2008.   The standards were set based on a capacity of 20 000 machine hours. During the year, 5100 units were produced.   What was Carvelle's fixed overhead volume variance? The standards were set based on a capacity of 20 000 machine hours. During the year, 5100 units were produced. Carvelle Cabinets set the following standard cost per unit for 2008.   The standards were set based on a capacity of 20 000 machine hours. During the year, 5100 units were produced.   What was Carvelle's fixed overhead volume variance? What was Carvelle's fixed overhead volume variance?

(Multiple Choice)
4.8/5
(87)

Flexible overhead budgets are based on standard input measures instead of units of output in a multiproduct firm.

(True/False)
4.9/5
(91)

One of the shortcomings of ABC is that it is not easy to account for common costs shared by more than one activity.

(True/False)
4.8/5
(76)

Why is the budget variance the real control variance, for fixed overhead?

(Multiple Choice)
4.7/5
(71)

Carvelle Cabinets set the following standard cost per unit for 2008. Carvelle Cabinets set the following standard cost per unit for 2008.   The standards were set based on a capacity of 20 000 machine hours. During the year, 5100 units were produced.   What was the total amount of under/overapplied overhead for the firm? The standards were set based on a capacity of 20 000 machine hours. During the year, 5100 units were produced. Carvelle Cabinets set the following standard cost per unit for 2008.   The standards were set based on a capacity of 20 000 machine hours. During the year, 5100 units were produced.   What was the total amount of under/overapplied overhead for the firm? What was the total amount of under/overapplied overhead for the firm?

(Multiple Choice)
4.8/5
(81)

Which of the following cannot cause an unfavourable variable overhead efficiency variance?

(Multiple Choice)
4.7/5
(73)

Master Products has the following information at the end of the year. Master Products has the following information at the end of the year.   What is Master Product's sales volume variance? What is Master Product's sales volume variance?

(Multiple Choice)
4.9/5
(77)

The budgeted costs per unit for a company are fixed costs $2 per unit; variable costs $3 per unit. What is the expected cost of producing 1005 units?

(Multiple Choice)
4.9/5
(80)

Which of the following statements is false?

(Multiple Choice)
4.8/5
(78)

A favourable overhead efficiency variance is the result of

(Multiple Choice)
4.9/5
(78)

Felter Company sold 8000 units of Product X last month. The actual production level was 9000 units. The budget selling price was $10, but the sales manager had to discount the products by 20 per cent before managing to sell these units. The sales price variance is

(Multiple Choice)
4.8/5
(79)
Showing 61 - 80 of 109