A favorable production-volume variance arises when manufacturing capacity planned for is NOT used.

(True/False)
4.9/5
(72)

If the production planners set the budgeted machine hours standards too tight,one could anticipate there would be a favorable variable overhead efficiency variance.

(True/False)
4.8/5
(85)

Answer the following questions using the information below: Sport-in Corporation manufactured 10,000 golf bags during April. The following fixed overhead data pertain to March: Actual Static Budget Production 20,000 units 20,500 units Machine-hours 5,100 hours 6,150 hours Fixed overhead cost for March \ 250,000 \ 258,300 -What is the amount of fixed overhead allocated to production?

(Multiple Choice)
4.9/5
(86)

At the start of the budget period,management will have made most decisions regarding the level of fixed overhead costs to be incurred.

(True/False)
4.8/5
(93)

A favorable fixed overhead flexible-budget variance indicates that actual fixed costs exceeded the lump-sum amount budgeted.

(True/False)
4.9/5
(91)

The amount reported for fixed overhead on the static budget is also reported ________.

(Multiple Choice)
4.9/5
(85)

Lungren has budgeted construction overhead for August of $260,000 for variable costs and $435,000 for fixed costs.Actual costs for the month totaled $275,000 for variable and $445,000 for fixed.Allocated fixed overhead totaled $440,000.The company tracks each item in an overhead control account before allocations are made to individual jobs.Spending variances for August were $10,000 unfavorable for variable and $10,000 unfavorable for fixed.The production-volume overhead variance was $5,000 favorable. Required: a.Make journal entries for the actual costs incurred. b.Make journal entries to record the variances for August.

(Essay)
4.8/5
(75)

Answer the following questions using the information below: Deocomfort Corporation manufactured 54,000 door jambs during September. The following fixed overhead data relates to September: Actual Static Budget Production 55,500 units 55,000 units Machine-hours 985 hours 1,100 hours Fixed overhead costs for September \ 50,500 \ 50,600 -What is the flexible-budget amount?

(Multiple Choice)
4.8/5
(65)

Answer the following questions using the information below: Zitrik Corporation manufactured 100,000 buckets during February. The variable overhead cost-allocation base is $5.00 per machine-hour. The following variable overhead data pertain to February: Actual Budgeted Production 90,000 units 90,000 units Machine-hours 9,800 hours 9,000 hours Variable overhead cost per machine-hour \ 5.15 \ 5.05 -What is the variable overhead efficiency variance?

(Multiple Choice)
4.8/5
(70)

Prod uction- Variances Spending Efficiency Volume Variable manufacturing overhead \ 7,500 \ 30,000 () Fixed manufacturing overhead \ 28,000 () \ 80,000 -The total overhead variance should be ________.

(Multiple Choice)
4.8/5
(70)

Use the following information to answer the following questions: Autogas Corporation manufactures industrial-sized gas furnaces and uses budgeted machine hours to allocate variable manufacturing overhead. The following information relates to the company's manufacturing overhead data: Budgeted output units 31,000 urits Budgeted machine-hours 16,585 hours Budgeted variable manufacturing overhead costs for 31,000 units \ 348,285 Actual output units produced 33,000 urits Actual machine-hours used 14,400 hours Actual variable manufacturing overhead costs \ 384,000 -What is the amount of the budgeted variable manufacturing overhead cost per unit?

(Multiple Choice)
4.8/5
(69)

Prod uction- Variances Spending Efficiency Volume Variable manufacturing overhead \ 7,500 \ 30,000 () Fixed manufacturing overhead \ 28,000 () \ 80,000 -The total production-volume variance should be ________.

(Multiple Choice)
4.8/5
(79)

Favorable overhead variances are always recorded with credits in a standard cost system.

(True/False)
5.0/5
(81)

Teecorp Company uses a flexible budget for its indirect manufacturing costs.For 2015,the company anticipated that it would produce 27,000 units with 4,800 machine-hours and 8,000 employee days.The costs and cost drivers were to be as follows: Fixed Variable Cost driver Product handling \ 45,000 \ 0.75 per unit Inspection 12,000 12.00 per 100 unit batch Utilities 600 6.00 per 100 unit batch Maintenance 1,250 0.25 per machine-hour Supplies 5.00 per employee day During the year,the company processed 26,500 units,worked 8,200 employee days,and had 4,850 machine-hours.The actual costs for 2015 were: Actual costs Product handling \ 65,000 Inspection 16,200 Utilities 2,220 Maintenance 2,850 Supplies 39,900 Required: a.Prepare the static budget using the overhead items above and then compute the static-budget variances. b.Prepare the flexible budget using the overhead items above and then compute the flexible-budget variances.

(Essay)
4.8/5
(78)

An unfavorable fixed overhead spending variance indicates that ________.

(Multiple Choice)
4.7/5
(83)

Prorated allocation of production-volume variance has the effect of approximating the allocation of fixed costs based on actual costs and actual output.

(True/False)
4.9/5
(86)

Answer the following questions using the information below: Skizone Company's 4-Variance Analysis: Production-Volume Spending Variance Efficiency Variance Variance Variable overhead \ 6,500 \ 12,000 No variance Fixed overhead (a) No variance \ 46,000 -Which of the following statements is true of Skizone's overhead variances?

(Multiple Choice)
4.8/5
(84)

The production volume variance arises only for variable overhead costs.

(True/False)
4.7/5
(75)

Prod uction- Variances Spending Efficiency Volume Variable manufacturing overhead \ 7,500 \ 30,000 () Fixed manufacturing overhead \ 28,000 () \ 80,000 -In the above table,the amounts for (A)and (B),respectively,are ________.

(Multiple Choice)
4.9/5
(75)

Answer the following questions using the information below: Sport-in Corporation manufactured 10,000 golf bags during April. The following fixed overhead data pertain to March: Actual Static Budget Production 20,000 units 20,500 units Machine-hours 5,100 hours 6,150 hours Fixed overhead cost for March \ 250,000 \ 258,300 -What is the flexible-budget amount?

(Multiple Choice)
5.0/5
(82)
Showing 81 - 100 of 176
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)