Exam 9: Material Requirements Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The least unit cost method of lot-sizing adds ordering,stock-out and inventory carrying cost for each trial lot size and divides by the number of units in each lot size,picking the lot size with the lowest unit cost.

(True/False)
4.8/5
(71)

Which of the following is the net requirement using an MRP program if the gross requirement is 1,000 and the inventory on hand is 500?

(Multiple Choice)
4.8/5
(84)

Which of the following is the planned-order release using an MRP program if the gross requirement is 670 and the inventory on hand is 600?

(Multiple Choice)
4.9/5
(69)

In a net change MRP system requirements and schedules are updated whenever a transaction is processed that has an impact on the item.

(True/False)
4.8/5
(71)

Net change MRP reflects the exact status of each item managed by the system in "real time."

(True/False)
4.8/5
(95)

Which of the following is an input to the master production schedule?

(Multiple Choice)
4.9/5
(77)

The economic order quantity (EOQ)lot sizing technique uses the "square root formula" to balance set-up cost,carrying cost and cost of stock-outs.

(True/False)
4.9/5
(76)

If annual demand is 12,000 units,annual holding cost is $15 per unit,and setup cost per order is $25,which of the following is the EOQ lot size?

(Multiple Choice)
4.9/5
(81)

MRP is a logical,easily understandable approach to the problem of determining the number of parts,components,and materials needed to produce each end item.

(True/False)
4.8/5
(86)