Multiple Choice
Which of the following is the planned-order release using an MRP program if the gross requirement is 670 and the inventory on hand is 600?
A) 670
B) 600
C) 530
D) 70
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified