Exam 14: Extension: Maintenance
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness, Strategy, and Productivity72 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design76 Questions
Exam 4: Extension: Reliability12 Questions
Exam 5: Strategic Capacity Planning for Products and Services106 Questions
Exam 5: Extension: Decision Theory123 Questions
Exam 6: Process Selection and Facility Layout150 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 7: Extension: Learning Curves68 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 8: Extension: The Transportation Model20 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 10: Extension: Acceptance Sampling65 Questions
Exam 11: Aggregate Planning and Master Scheduling88 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management161 Questions
Exam 14: Jit and Lean Operations87 Questions
Exam 14: Extension: Maintenance38 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming111 Questions
Select questions type
Which of the following would not improve the performance of a breakdown program?
(Multiple Choice)
5.0/5
(88)
In the broadest sense, equipment and facilities preventive maintenance extends back to the:
(Multiple Choice)
4.9/5
(70)
The goal of maintenance is to maintain the productive system in good working order while minimizing:
(Multiple Choice)
4.9/5
(84)
Suppose that for a particular piece of machinery, the frequency distribution of monthly breakdowns is as follows: Number of Breakdowns Prob. 0 0.40 1 0.30 2 0.15 3 0.10 4 0.05 The cost of a breakdown is $2,000, and the cost of a preventive maintenance program is $2,000 per month. If the preventive maintenance program is adopted, the probability of a machine breakdown is negligible. How much better off per month would the firm be if it adopted preventive maintenance?
(Multiple Choice)
4.9/5
(76)
Preventive maintenance is generally scheduled on the basis of:
(Multiple Choice)
4.9/5
(75)
Attempting to determine when preventive maintenance activities should be performed is called:
(Multiple Choice)
4.9/5
(77)
The average time before breakdown of a machine is normally distributed and has a mean of 18 weeks and a standard deviation of three weeks. If breakdown cost averages $2,000 and preventive maintenance costs $1,400, what is the optimal preventive maintenance interval?
(Multiple Choice)
4.8/5
(78)
Breakdown programs often are prioritized such that some equipment gets a lot of attention and other equipment gets very little. This typically reflects the fact that breakdowns are consistent with:
(Multiple Choice)
5.0/5
(75)
The average time before breakdown of a machine is normally distributed and has a mean of seven weeks and a standard deviation of 1.5 weeks. If breakdown cost averages $2,500 and preventive maintenance costs $500, what is the optimal preventive maintenance interval?
(Essay)
4.8/5
(74)
Pareto analysis (using the 80/20 rule) is one method of determining when preventive maintenance activities should be performed.
(True/False)
4.9/5
(80)
Breakdown maintenance is _____________; preventive maintenance is _________.
(Multiple Choice)
4.9/5
(88)
Ideally, preventive maintenance will be performed before a breakdown or failure.
(True/False)
4.8/5
(66)
Maintenance activities are often organized into the following two groups:
(Multiple Choice)
4.8/5
(75)
Showing 21 - 38 of 38