Which of the following is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network?

(Multiple Choice)
5.0/5
(75)

What is the total cost of reducing the project to 18 weeks?

(Short Answer)
4.9/5
(73)

Which of the following lead to simulation being a useful tool with uncertain activity times.

(Multiple Choice)
4.8/5
(84)

Which of the following is not a limitation of PERT and similar project-scheduling techniques?

(Multiple Choice)
4.8/5
(87)

In the probabilistic approach to project network analysis, the time estimate annotated "tm" for any activity is the:

(Multiple Choice)
4.9/5
(73)

What is the estimated expected (mean) time for activity D?

(Multiple Choice)
4.9/5
(84)

A sequence of activities that leads from the starting node to the finishing node is called a _______.

(Multiple Choice)
4.9/5
(86)

The main function of dummy activities is to clarify relationships in network diagrams.

(True/False)
4.8/5
(84)

The project computing algorithm requires both a forward and backward pass.

(True/False)
4.8/5
(76)

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.

(True/False)
4.8/5
(81)

Which of the following are limitations of PERT? (I) Time estimates may include a fudge factor. (II) Important activities may be overlooked. (III) It is an after-the-fact analysis.

(Multiple Choice)
4.9/5
(78)

Activity D has an optimistic time of 3 days, a pessimistic time of 9 days, and a most likely time of 4 days.Determine its expected time and variance.

(Essay)
4.9/5
(81)

In crashing this project, which activity should be the first to be reduced?

(Short Answer)
4.8/5
(73)

A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days.The expected time (in days) of this activity is:

(Multiple Choice)
4.8/5
(79)

In project network analysis, "slack" refers to the difference between:

(Multiple Choice)
4.7/5
(77)

Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7.Activity 5-7 has an expected time of five and an ES time of six.Activity 6-7 has an expected time of seven and an ES time of seven.Activity 7-8 has an expected time of 10.The ES for activity 7-8 is:

(Multiple Choice)
4.7/5
(74)

What are the estimated expected (mean) times (in weeks) for activities A-H?

(Short Answer)