Exam 17: Project Management
Exam 1: Introduction to Operations Management70 Questions
Exam 2: Competitiveness, Strategy, and Productivity73 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design77 Questions
Exam 5: Strategic Capacity Planning for Products and Services103 Questions
Exam 6: Process Selection and Facility Layout151 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 11: Aggregate Planning and Master Scheduling81 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management162 Questions
Exam 14: Jit and Lean Operations88 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming105 Questions
Exam 20: Extension 4: Reliability10 Questions
Exam 21: Extension 5: Decision Theory126 Questions
Exam 22: Extension 7: Learning Curves68 Questions
Exam 23: Extension 8: The Transportation Model20 Questions
Exam 24: Extension 10: Acceptance Sampling65 Questions
Exam 25: Extension 14: Maintenance38 Questions
Select questions type
Project management differs from management of more traditional activities mainly because of:
(Multiple Choice)
4.9/5
(82)
Prepare a crashing plan for the following project that will reduce the project duration by three weeks.
(Essay)
5.0/5
(91)
The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path.
(True/False)
4.9/5
(76)
What is the probability that the critical path for this project will be completed within 200 days?
(Multiple Choice)
4.9/5
(73)
The optimum project length in crashing occurs where the cumulative cost of crashing equals savings in the indirect costs.
(True/False)
4.7/5
(79)
What is the estimated expected (mean) time for project completion?
(Multiple Choice)
4.8/5
(76)
What is the estimated expected (mean) time for project completion?
(Multiple Choice)
4.8/5
(73)
If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path would not be a factor in assessing the probability of finishing the project on time.
(True/False)
4.9/5
(81)
Given the network diagram below, determine the probability that the project will finish within 26 weeks of its start.Times on the diagram are in weeks.
(Essay)
4.8/5
(76)
Many activities have slack time; if we add these slack times together, this represents the potential improvement in early completion for the project.
(True/False)
4.8/5
(67)
A hierarchical (vertical) listing of what must be done during a project is called matrix.
(True/False)
4.9/5
(82)
Which of the following is not typically treated as part of a project life cycle?
(Multiple Choice)
4.8/5
(79)
Which of the following is not an element of the project management triangle?
(Multiple Choice)
4.8/5
(74)
If two consecutive activities have shared slack, this means that each of them can use only half of the slack without delaying completion of the project.
(True/False)
4.7/5
(79)
In order to determine the probability of timely project completion, it is sometimes necessary to take into account paths other than the critical path.
(True/False)
4.9/5
(85)
The sum of times of the longest path in a network indicates expected project completion time, and the activities represent the critical activities.
(True/False)
4.8/5
(74)
Project managers are sometimes able to reduce indirect project costs by increasing direct costs.
(True/False)
4.9/5
(65)
What is the estimated expected (mean) time for project completion?
(Multiple Choice)
4.9/5
(93)