Exam 17: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

What is the estimated slack time for activity W?

(Multiple Choice)
4.8/5
(70)

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days.The standard deviation of the critical path is:

(Multiple Choice)
4.7/5
(73)

The task of identifying risks should involve everyone associated with the project.

(True/False)
4.7/5
(76)

To _____ an activity means to shorten the time it will take.

(Multiple Choice)
4.8/5
(77)

Given this information about activity 3-4: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount of slack associated with the activity is:

(Multiple Choice)
4.8/5
(77)

What is the estimated standard deviation in the time for activity D?

(Multiple Choice)
4.9/5
(93)

In a project network the critical path is the sequence of activities which has the:

(Multiple Choice)
4.9/5
(67)

The total cost of crashing any one activity should never exceed 20% of the total cost of the original project.

(True/False)
4.9/5
(69)

Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17.Its slack is:

(Multiple Choice)
4.8/5
(73)

What is the estimated standard deviation (in weeks) for the critical path completion time?

(Short Answer)
4.9/5
(74)

The probability that the project will go beyond the desired time is equal to one minus the joint probability that all paths will be completed within the desired time.

(True/False)
4.9/5
(70)

The expected duration of this project is:

(Multiple Choice)
5.0/5
(73)

In crashing this project to 18 weeks, which activities (in order of selection) will be reduced? A.

(Essay)
4.8/5
(85)

If two consecutive activities on the same path each have two days of activity slack, this means that each of them can be delayed by two days without delaying the project.

(True/False)
4.8/5
(68)

The critical path for the network shown is:

(Multiple Choice)
5.0/5
(72)

What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.9/5
(71)

If an activity is determined to be on the critical, that means that it, and perhaps other, will affect project ____________.

(Multiple Choice)
4.9/5
(82)

In PERT, the path with the fewest activities is referred to as the critical path.

(True/False)
4.8/5
(94)

Most likely time generally is more than optimistic time.

(True/False)
4.7/5
(94)

Slack time is equal to LS-ES or LF-EF.

(True/False)
4.8/5
(87)