The path in a network with the average length of time to completion is called the critical path.

(True/False)
4.9/5
(87)

What is the estimated expected (mean) time for activity E?

(Multiple Choice)
4.7/5
(86)

What are the estimated slack times (in weeks) for activities A-H?

(Short Answer)
4.7/5
(82)

What is the estimated standard deviation in the time for activity Z?

(Multiple Choice)
4.8/5
(75)

The earliest finish time for an activity is equal to the latest finish time minus the activity time.

(True/False)
4.9/5
(77)

When developing probabilistic estimates of project duration, it is necessary to know which of the following?

(Multiple Choice)
4.8/5
(91)

What is the estimated slack time for Activity E?

(Multiple Choice)
4.9/5
(79)

Concerning PERT and CPM:

(Multiple Choice)
4.8/5
(85)

What are the estimated standard deviations (in weeks) in the times for activities A-H?

(Short Answer)
4.9/5
(85)

In "crashing" a project, a manager will generally focus on activities which:

(Multiple Choice)
4.9/5
(76)

What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.7/5
(80)

Which of the following is not a form of risk reduction in project management?

(Multiple Choice)
4.9/5
(73)

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the earliest finish time for activity 10-11 (far right hand side), if the earliest start time of 8-10 (upper left hand side) is 12, and the earliest start time of 9-10 (lower left hand side) is 13? What is the earliest finish time for activity 10-11 (far right hand side), if the earliest start time of 8-10 (upper left hand side) is 12, and the earliest start time of 9-10 (lower left hand side) is 13?

(Multiple Choice)
4.7/5
(77)

A node has one entering activity, a, and two leaving activities, b and c.Given the following information, determine the latest starting time for activity a: EFb = 15, EFc = 17, LFb = 24, LFc = 27; activity times are a = 4, b = 6, c = 8.

(Multiple Choice)
4.8/5
(81)

At which point does crashing of a project cease?

(Multiple Choice)
4.9/5
(82)

The advantage(s) a precedence diagram has over a Gantt chart is(are):

(Multiple Choice)
4.8/5
(73)

A project consists of nine major activities, as shown below.There are three separate paths in the network: a-c-f, b-d-g, and e-h-i. (A) What is expected project duration time? (B) Determine the probability that the project will take more than 35 weeks to complete.(All times are in weeks.)

(Essay)
4.9/5
(66)

The latest starting time for an activity is equal to the latest finish time minus the activity time.

(True/False)
4.9/5
(67)

Which of the following would probably not involve the use of PERT?

(Multiple Choice)
5.0/5
(75)

Activities not on the critical path have a slack time equal to zero.

(True/False)
4.9/5
(86)