Solved

A Project Consists of Nine Major Activities, as Shown Below

Question 77

Essay

A project consists of nine major activities, as shown below.There are three separate paths in the network: a-c-f, b-d-g, and e-h-i.
(A) What is expected project duration time?
(B) Determine the probability that the project will take more than 35 weeks to complete.(All times are in weeks.)

Correct Answer:

verifed

Verified

blured image blured image blured image A) Expected duration = 32 w...