    Activity D Has an Optimistic Time of 3 Days, a Pessimistic
Solved

Activity D Has an Optimistic Time of 3 Days, a Pessimistic

Question 132

Question 132

Essay

Activity D has an optimistic time of 3 days, a pessimistic time of 9 days, and a most likely time of 4 days.Determine its expected time and variance.

Correct Answer:

verifed

Verified

te = (to + 4tm + tp)/6 =...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q19: Activity 7-8 is directly preceded by two

Q25: A PERT/CPM activity has an optimistic time

Q71: The earliest finish time for an activity

Q96: The main function of dummy activities is

Q107: Which of the following are limitations of

Q113: In project network analysis, "slack" refers to

Q127: A sequence of activities that leads from

Q129: The project computing algorithm requires both a

Q133: In crashing this project, which activity should

Q137: What are the estimated expected (mean) times

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines