Exam 17: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path.

(True/False)
4.7/5
(72)

A hierarchical listing of what must be done in a project is called a

(Multiple Choice)
4.9/5
(82)

Many activities have slack time; if we add these slack times together, this represents the potential improvement in early completion for the project.

(True/False)
4.9/5
(70)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity E? What is the estimated slack time for activity E?

(Multiple Choice)
4.9/5
(80)

Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days. Its expected time (in days)is approximately

(Multiple Choice)
4.8/5
(85)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity D? What is the estimated standard deviation in the time for activity D?

(Multiple Choice)
4.8/5
(79)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)time for activity E? What is the estimated expected (mean)time for activity E?

(Multiple Choice)
4.8/5
(77)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity D? What is the estimated slack time for activity D?

(Multiple Choice)
4.8/5
(87)

Once a project is approved and underway, project managers are only responsible for effectively managing time and costs which, if done well, will assure project completion on time and on budget.

(True/False)
4.9/5
(81)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.8/5
(85)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
5.0/5
(92)

A sequence of activities that leads from the starting node to the finishing node is called a

(Multiple Choice)
4.9/5
(89)

In project network analysis, "slack" refers to the difference between

(Multiple Choice)
4.7/5
(72)

Matrix organizations transfer control of workers to project managers for the duration of the project.

(True/False)
5.0/5
(69)

One upside to terminating a project that is not going as well as planned is that

(Multiple Choice)
4.7/5
(93)

Once a project is underway, the project manager usually is not responsible for effectively managing

(Multiple Choice)
4.7/5
(93)

Path probabilities are calculated by dividing path mean by path standard deviations.

(True/False)
4.7/5
(74)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that the critical path for this project will be completed within 200 days? What is the probability that the critical path for this project will be completed within 200 days?

(Multiple Choice)
4.9/5
(92)
Showing 101 - 118 of 118
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)