Exam 17: Project Management
Exam 1: Introduction to Operations Management78 Questions
Exam 2: Competitiveness, Strategy, and Productivity75 Questions
Exam 3: Forecasting144 Questions
Exam 4: Product and Service Design100 Questions
Exam 5: Strategic Capacity Planning for Products and Services210 Questions
Exam 6: Process Selection and Facility Layout137 Questions
Exam 7: Work Design and Measurement200 Questions
Exam 8: Location Planning and Analysis65 Questions
Exam 9: Management of Quality101 Questions
Exam 10: Quality Control117 Questions
Exam 11: Aggregate Planning and Master Scheduling80 Questions
Exam 12: Inventory Management134 Questions
Exam 13: MRP and ERP85 Questions
Exam 14: Jit and Lean Operations126 Questions
Exam 15: Supply Chain Management91 Questions
Exam 16: Scheduling102 Questions
Exam 17: Project Management118 Questions
Exam 18: Management of Waiting Lines68 Questions
Exam 19: Linear Programming98 Questions
Select questions type
Consider the following work breakdown structure:
What is the probability that the critical path for this project will be completed within 52 weeks?
(Multiple Choice)
4.8/5
(92)
Consider the following work breakdown structure:
What is the estimated slack time for activity W?
(Multiple Choice)
4.9/5
(99)
Which decision in project management has typical factors that include establishing appropriate metrics for evaluating the project and managing equipment?
(Multiple Choice)
4.7/5
(90)
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is
(Multiple Choice)
4.8/5
(67)
Which phase of the project life cycle happens in conjunction with project execution?
(Multiple Choice)
4.8/5
(88)
A disadvantage of activity-on-node diagrams is the occasional need for dummy activities.
(True/False)
4.9/5
(84)
Which of the following is not a form of risk reduction in project management?
(Multiple Choice)
5.0/5
(90)
The project computing algorithm requires both a forward and a backward pass.
(True/False)
4.9/5
(70)
Consider the portion of a project depicted by this graph:
What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23?
(Multiple Choice)
4.9/5
(85)
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.
(True/False)
4.7/5
(81)
Which of the following is not typically treated as part of a project life cycle?
(Multiple Choice)
4.9/5
(77)
To _____ an activity means to shorten the time it will take.
(Multiple Choice)
4.8/5
(78)
The project management strategy of injecting additional resources in order to reduce the length of the project is called
(Multiple Choice)
4.9/5
(65)
The sum of times of the longest path in a network indicates expected project duration, and the activities represent the critical activities.
(True/False)
4.8/5
(82)
Project management differs from management of more traditional activities mainly because of:
(I)its limited time frame.(II)its unique, defined set of activities.(III)the requirement for use of the appropriate resources.(IV)the need for planning and execution.
(Multiple Choice)
4.9/5
(66)
An advantage of Gantt charts in project management is that they identify which activities can be delayed without delaying the overall project.
(True/False)
4.7/5
(79)
The advantage a precedence diagram has over a Gantt chart is
(Multiple Choice)
4.9/5
(68)
The costs associated with risk events tend to be lower near the beginning of a project and higher near the end of the project.
(True/False)
4.9/5
(86)
Consider the following work breakdown structure:
What is the estimated expected (mean)time for project completion?
(Multiple Choice)
4.8/5
(84)