Exam 17: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that the critical path for this project will be completed within 52 weeks? What is the probability that the critical path for this project will be completed within 52 weeks?

(Multiple Choice)
4.8/5
(92)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity W? What is the estimated slack time for activity W?

(Multiple Choice)
4.9/5
(99)

Shortening activity durations is called

(Multiple Choice)
4.8/5
(87)

Which decision in project management has typical factors that include establishing appropriate metrics for evaluating the project and managing equipment?

(Multiple Choice)
4.7/5
(90)

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is

(Multiple Choice)
4.8/5
(67)

Which phase of the project life cycle happens in conjunction with project execution?

(Multiple Choice)
4.8/5
(88)

A disadvantage of activity-on-node diagrams is the occasional need for dummy activities.

(True/False)
4.9/5
(84)

Which of the following is not a form of risk reduction in project management?

(Multiple Choice)
5.0/5
(90)

The project computing algorithm requires both a forward and a backward pass.

(True/False)
4.9/5
(70)

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23? What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23?

(Multiple Choice)
4.9/5
(85)

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.

(True/False)
4.7/5
(81)

Which of the following is not typically treated as part of a project life cycle?

(Multiple Choice)
4.9/5
(77)

To _____ an activity means to shorten the time it will take.

(Multiple Choice)
4.8/5
(78)

The project management strategy of injecting additional resources in order to reduce the length of the project is called

(Multiple Choice)
4.9/5
(65)

The sum of times of the longest path in a network indicates expected project duration, and the activities represent the critical activities.

(True/False)
4.8/5
(82)

Project management differs from management of more traditional activities mainly because of: (I)its limited time frame.(II)its unique, defined set of activities.(III)the requirement for use of the appropriate resources.(IV)the need for planning and execution.

(Multiple Choice)
4.9/5
(66)

An advantage of Gantt charts in project management is that they identify which activities can be delayed without delaying the overall project.

(True/False)
4.7/5
(79)

The advantage a precedence diagram has over a Gantt chart is

(Multiple Choice)
4.9/5
(68)

The costs associated with risk events tend to be lower near the beginning of a project and higher near the end of the project.

(True/False)
4.9/5
(86)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)time for project completion? What is the estimated expected (mean)time for project completion?

(Multiple Choice)
4.8/5
(84)
Showing 61 - 80 of 118
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)