Exam 17: Project Management
Exam 1: Introduction to Operations Management78 Questions
Exam 2: Competitiveness, Strategy, and Productivity75 Questions
Exam 3: Forecasting144 Questions
Exam 4: Product and Service Design100 Questions
Exam 5: Strategic Capacity Planning for Products and Services210 Questions
Exam 6: Process Selection and Facility Layout137 Questions
Exam 7: Work Design and Measurement200 Questions
Exam 8: Location Planning and Analysis65 Questions
Exam 9: Management of Quality101 Questions
Exam 10: Quality Control117 Questions
Exam 11: Aggregate Planning and Master Scheduling80 Questions
Exam 12: Inventory Management134 Questions
Exam 13: MRP and ERP85 Questions
Exam 14: Jit and Lean Operations126 Questions
Exam 15: Supply Chain Management91 Questions
Exam 16: Scheduling102 Questions
Exam 17: Project Management118 Questions
Exam 18: Management of Waiting Lines68 Questions
Exam 19: Linear Programming98 Questions
Select questions type
If two consecutive activities on the same path each have two days of activity slack, this means that each of them can be delayed by two days without delaying the project.
(True/False)
4.8/5
(78)
When developing probabilistic estimates of project duration, it is necessary to know which of the following?
(Multiple Choice)
4.9/5
(79)
Some organizations use a matrix organization to integrate the activities of specialists within a functional framework.
(True/False)
4.9/5
(70)
Which of the following is not true about the use of dummy activities in project networking?
(Multiple Choice)
4.8/5
(68)
Which of the following leads to simulation being a useful tool with uncertain activity times?
(Multiple Choice)
4.8/5
(69)
Which of the following are advantages of PERT and CPM?
(I)It is visual.(II)It is automatically updated.(III)Activities that need to be watched closely can be identified.
(Multiple Choice)
4.9/5
(71)
Which of the following is not an element of the project management triangle?
(Multiple Choice)
4.8/5
(79)
Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17. Its slack is
(Multiple Choice)
4.8/5
(76)
Consider the portion of a project depicted by this graph:
What is the earliest finish time for activity 10-11 (far right-hand side)if the earliest start time of 8-10 (upper left-hand side)is 12 and the earliest start time of 9-10 (lower left-hand side)is 13?
(Multiple Choice)
4.8/5
(97)
There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to
(Multiple Choice)
4.7/5
(81)
Given this information about activity 3-4: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount of slack associated with the activity is
(Multiple Choice)
4.8/5
(84)
Deterministic networks use three time estimates-shortest, most likely, and longest-for each activity in order to best determine the activity's estimated time.
(True/False)
4.8/5
(84)
Consider the following work breakdown structure:
What is the probability that this project will be completed within 205 days?
(Multiple Choice)
4.9/5
(72)
The main function of dummy activities is to clarify relationships in network diagrams.
(True/False)
4.7/5
(86)
Which of the following is not characteristic of good risk management?
(Multiple Choice)
4.8/5
(95)
A project is represented by the following diagram:
The expected duration of this project is:
(Multiple Choice)
4.9/5
(73)
In which phase of the project life cycle is the work conducted?
(Multiple Choice)
4.9/5
(74)
The network diagram shows sequential relationships among major activities on a project.
(True/False)
4.8/5
(81)