If two consecutive activities on the same path each have two days of activity slack, this means that each of them can be delayed by two days without delaying the project.

(True/False)
4.8/5
(78)

When developing probabilistic estimates of project duration, it is necessary to know which of the following?

(Multiple Choice)
4.9/5
(79)

Some organizations use a matrix organization to integrate the activities of specialists within a functional framework.

(True/False)
4.9/5
(70)

Which of the following is not true about the use of dummy activities in project networking?

(Multiple Choice)
4.8/5
(68)

Which of the following leads to simulation being a useful tool with uncertain activity times?

(Multiple Choice)
4.8/5
(69)

Which of the following are advantages of PERT and CPM? (I)It is visual.(II)It is automatically updated.(III)Activities that need to be watched closely can be identified.

(Multiple Choice)
4.9/5
(71)

Which of the following is not an element of the project management triangle?

(Multiple Choice)
4.8/5
(79)

Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17. Its slack is

(Multiple Choice)
4.8/5
(76)

The basis for use of the beta distribution in PERT is

(Multiple Choice)
4.8/5
(79)

The higher the node number, the longer the activity will take.

(True/False)
4.8/5
(93)

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the earliest finish time for activity 10-11 (far right-hand side)if the earliest start time of 8-10 (upper left-hand side)is 12 and the earliest start time of 9-10 (lower left-hand side)is 13? What is the earliest finish time for activity 10-11 (far right-hand side)if the earliest start time of 8-10 (upper left-hand side)is 12 and the earliest start time of 9-10 (lower left-hand side)is 13?

(Multiple Choice)
4.8/5
(97)

There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to

(Multiple Choice)
4.7/5
(81)

Given this information about activity 3-4: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount of slack associated with the activity is

(Multiple Choice)
4.8/5
(84)

Deterministic networks use three time estimates-shortest, most likely, and longest-for each activity in order to best determine the activity's estimated time.

(True/False)
4.8/5
(84)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that this project will be completed within 205 days? What is the probability that this project will be completed within 205 days?

(Multiple Choice)
4.9/5
(72)

The main function of dummy activities is to clarify relationships in network diagrams.

(True/False)
4.7/5
(86)

Which of the following is not characteristic of good risk management?

(Multiple Choice)
4.8/5
(95)

A project is represented by the following diagram: A project is represented by the following diagram:   The expected duration of this project is: The expected duration of this project is:

(Multiple Choice)
4.9/5
(73)

In which phase of the project life cycle is the work conducted?

(Multiple Choice)
4.9/5
(74)

The network diagram shows sequential relationships among major activities on a project.

(True/False)
4.8/5
(81)