Exam 3: Project Management
Exam 1: Operations and Productivity138 Questions
Exam 2: Operations Strategy in a Global Environment134 Questions
Exam 3: Project Management131 Questions
Exam 4: Forecasting148 Questions
Exam 5: Design of Goods and Services126 Questions
Exam 6: Managing Quality226 Questions
Exam 7: Process Strategies259 Questions
Exam 8: Location Strategies233 Questions
Exam 9: Human Resources, Job Design, and Work Measurement321 Questions
Exam 10: Supply Chain Management158 Questions
Exam 11: Inventory Management230 Questions
Exam 12: Aggregate Planning and Sop122 Questions
Exam 13: Material Requirements Planning Mrp and Erp133 Questions
Exam 14: Short-Term Scheduling124 Questions
Exam 15: Lean Operations122 Questions
Exam 16: Maintenance and Reliability119 Questions
Exam 17: Decision-Making Tools101 Questions
Exam 18: Linear Programming102 Questions
Exam 19: Transportation Models92 Questions
Exam 20: Waiting-Line Models126 Questions
Exam 21: Learning Curves114 Questions
Exam 22: Simulation78 Questions
Exam 23: Applying Analytics to Big Data in Operations Management61 Questions
Select questions type
A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before which day (rounded to nearest day)?
(Multiple Choice)
4.8/5
(86)
Two activities on different critical paths that share no common nodes are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, the manager should crash activity(ies) ________, adding ________ to project cost. 
(Multiple Choice)
5.0/5
(83)
Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?
(Multiple Choice)
4.9/5
(80)
The ES of an activity that has only one predecessor is simply the EF of that predecessor.
(True/False)
4.8/5
(86)
What are the earliest activity start time and latest activity start time, and how are they computed?
(Essay)
4.7/5
(84)
Which of the following statements regarding Bechtel is NOT true?
(Multiple Choice)
4.9/5
(72)
The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates.
(True/False)
4.8/5
(71)
The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6.
(a) What task must be on the critical path, regardless of activity durations?
(b) What is the duration of path A-B-E-H-J?
(c) What is the critical path of this network?
(d) What is the length of the critical path?
(e) What is slack time at activity H?
(f) What is the Late Finish of activity H?
(g) If activity C was delayed by six time units, what would happen to the project duration?
(Essay)
4.9/5
(82)
A network consists of the activities in the following list. Times are given in weeks.
(a) Draw the network diagram.
(b) Calculate the ES, EF, LS, LF, and Slack for each activity.
(c) What is project completion time?
(Essay)
4.7/5
(84)
The critical path for the network activities shown below is ________ with duration ________. 
(Multiple Choice)
4.8/5
(76)
A network has been crashed to the point where all activities are critical. Additional crashing:
(Multiple Choice)
5.0/5
(66)
The bell curve is often appropriate for determining the expected value and variance for activity completion times.
(True/False)
4.8/5
(94)
Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is definitely TRUE?
(Multiple Choice)
4.9/5
(67)
A project organization works best for an organization when the project resides in only one of its functional areas.
(True/False)
4.8/5
(84)
Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost. 
(Multiple Choice)
4.8/5
(100)
A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. What is the probability that the project can be completed between days 114 and 120?
(Multiple Choice)
4.8/5
(88)
Which of the following statements regarding CPM networks is TRUE?
(Multiple Choice)