Exam 3: Project Management
Exam 1: Operations and Productivity138 Questions
Exam 2: Operations Strategy in a Global Environment134 Questions
Exam 3: Project Management131 Questions
Exam 4: Forecasting148 Questions
Exam 5: Design of Goods and Services126 Questions
Exam 6: Managing Quality226 Questions
Exam 7: Process Strategies259 Questions
Exam 8: Location Strategies233 Questions
Exam 9: Human Resources, Job Design, and Work Measurement321 Questions
Exam 10: Supply Chain Management158 Questions
Exam 11: Inventory Management230 Questions
Exam 12: Aggregate Planning and Sop122 Questions
Exam 13: Material Requirements Planning Mrp and Erp133 Questions
Exam 14: Short-Term Scheduling124 Questions
Exam 15: Lean Operations122 Questions
Exam 16: Maintenance and Reliability119 Questions
Exam 17: Decision-Making Tools101 Questions
Exam 18: Linear Programming102 Questions
Exam 19: Transportation Models92 Questions
Exam 20: Waiting-Line Models126 Questions
Exam 21: Learning Curves114 Questions
Exam 22: Simulation78 Questions
Exam 23: Applying Analytics to Big Data in Operations Management61 Questions
Select questions type
Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 22. Which of the following is definitely TRUE?
(Multiple Choice)
4.9/5
(73)
An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 10. What is its expected activity time?
(Multiple Choice)
4.8/5
(76)
Which of the following is NOT performed by Microsoft Project?
(Multiple Choice)
4.7/5
(93)
Match the following steps in Microsoft's development of Windows 10 to their respective WBS level. Step Level
Develop Windows 10 Operating System ?
System Testing ?
Compatible with Windows 8 ?
Develop GUI's ?
Module Testing ?
(Multiple Choice)
4.9/5
(98)
Work breakdown structure is a useful tool in project management because it addresses the timing of individual work elements.
(True/False)
4.7/5
(67)
PERT, but not CPM, has the ability to consider the precedence relationships in a project.
(True/False)
4.8/5
(79)
A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?
(Multiple Choice)
4.9/5
(67)
Slack is the amount of time an activity can be delayed without delaying the entire project.
(True/False)
5.0/5
(87)
The shortest of all paths through the network is the critical path.
(True/False)
4.8/5
(79)
The ________ distribution is appropriate for calculating expected activity times and activity variances in PERT networks.
(Short Answer)
4.8/5
(74)
Ethical issues that can arise in projects include gifts from contractors, pressure to mask delays with false status reports, false reports for charges of time and expenses, and pressure to compromise project quality to meet bonuses or avoid penalties related to schedules.
(True/False)
4.8/5
(87)
Describe in words how to calculate a project's standard deviation. What assumption allows that calculation to be accurate?
(Essay)
4.8/5
(65)
The expected activity time in PERT analysis is calculated as:
(Multiple Choice)
4.9/5
(89)
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take less than 224 days to complete?
(Multiple Choice)
4.8/5
(80)
Which of the following projects was NOT completed by Bechtel?
(Multiple Choice)
4.9/5
(73)
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
(a) Identify the activities on the critical path.
(b) What is the duration of the critical path?
(c) Calculate the amount of slack time at activity H.
(d) If activity I were delayed by ten time units, what would be the impact on the project duration?
(Essay)
4.9/5
(93)