Exam 3: Project Management
Exam 1: Operations and Productivity138 Questions
Exam 2: Operations Strategy in a Global Environment134 Questions
Exam 3: Project Management131 Questions
Exam 4: Forecasting148 Questions
Exam 5: Design of Goods and Services126 Questions
Exam 6: Managing Quality226 Questions
Exam 7: Process Strategies259 Questions
Exam 8: Location Strategies233 Questions
Exam 9: Human Resources, Job Design, and Work Measurement321 Questions
Exam 10: Supply Chain Management158 Questions
Exam 11: Inventory Management230 Questions
Exam 12: Aggregate Planning and Sop122 Questions
Exam 13: Material Requirements Planning Mrp and Erp133 Questions
Exam 14: Short-Term Scheduling124 Questions
Exam 15: Lean Operations122 Questions
Exam 16: Maintenance and Reliability119 Questions
Exam 17: Decision-Making Tools101 Questions
Exam 18: Linear Programming102 Questions
Exam 19: Transportation Models92 Questions
Exam 20: Waiting-Line Models126 Questions
Exam 21: Learning Curves114 Questions
Exam 22: Simulation78 Questions
Exam 23: Applying Analytics to Big Data in Operations Management61 Questions
Select questions type
The ________ distribution is used by PERT analysis to calculate expected activity times and variances.
(Multiple Choice)
4.9/5
(80)
Ill-defined projects are typified by software development and new technology.
(True/False)
4.9/5
(76)
The critical path for the network activities shown below is ________ with duration ________. 
(Multiple Choice)
4.9/5
(71)
Variation in activities that are not on the critical path cannot affect the overall project completion time.
(True/False)
4.7/5
(86)
A(n) ________ divides a project into more and more detailed components.
(Short Answer)
4.8/5
(74)
The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.
(True/False)
4.9/5
(85)
PERT calculations typically include the duration variance of each activity. What is the purpose of this calculation, i.e. what's the role of variances in PERT analysis?
(Essay)
4.8/5
(65)
What are the three phases of a project? Describe each in a sentence or two.
(Essay)
4.9/5
(90)
One responsibility of a project manager is to make sure that the project meets its quality goals.
(True/False)
4.7/5
(89)
An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. What is its expected activity time?
(Multiple Choice)
4.8/5
(75)
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 10. What is its expected activity time and variance?
(Multiple Choice)
4.7/5
(78)
A partially solved PERT problem is detailed in the table below. Times are given in weeks.
(a) Calculate the expected time and variance for each activity. Enter these values in the appropriate columns in the table above.
(b) Which activities form the critical path?
(c) What is the estimated time of the critical path?
(d) What are the project variance and the project standard deviation?
(e) What is the probability of completion of the project before week 42?
(Essay)
4.7/5
(77)
WBS stands for which of the following project management tools?
(Multiple Choice)
4.9/5
(71)
Which of the following statements regarding Gantt charts is TRUE?
(Multiple Choice)
4.8/5
(84)
In PERT analysis, the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.
(True/False)
4.7/5
(71)
Explain why the critical path is the longest, not the shortest, path through a network.
(Essay)
4.8/5
(78)
Showing 21 - 40 of 131
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)