Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The phases of project management are:

(Multiple Choice)
4.9/5
(71)

The ________ distribution is used by PERT analysis to calculate expected activity times and variances.

(Multiple Choice)
4.9/5
(80)

Ill-defined projects are typified by software development and new technology.

(True/False)
4.9/5
(76)

The critical path for the network activities shown below is ________ with duration ________. The critical path for the network activities shown below is ________ with duration ________.

(Multiple Choice)
4.9/5
(71)

Variation in activities that are not on the critical path cannot affect the overall project completion time.

(True/False)
4.7/5
(86)

A(n) ________ divides a project into more and more detailed components.

(Short Answer)
4.8/5
(74)

The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.

(True/False)
4.9/5
(85)

What is a project organization?

(Essay)
4.9/5
(83)

PERT calculations typically include the duration variance of each activity. What is the purpose of this calculation, i.e. what's the role of variances in PERT analysis?

(Essay)
4.8/5
(65)

What are the three phases of a project? Describe each in a sentence or two.

(Essay)
4.9/5
(90)

One responsibility of a project manager is to make sure that the project meets its quality goals.

(True/False)
4.7/5
(89)

An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. What is its expected activity time?

(Multiple Choice)
4.8/5
(75)

An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 10. What is its expected activity time and variance?

(Multiple Choice)
4.7/5
(78)

The main difference between PERT and CPM is that:

(Multiple Choice)
4.8/5
(93)

What is the basic difference between PERT and CPM?

(Essay)
4.8/5
(71)

A partially solved PERT problem is detailed in the table below. Times are given in weeks. A partially solved PERT problem is detailed in the table below. Times are given in weeks.    (a) Calculate the expected time and variance for each activity. Enter these values in the appropriate columns in the table above. (b) Which activities form the critical path? (c) What is the estimated time of the critical path? (d) What are the project variance and the project standard deviation? (e) What is the probability of completion of the project before week 42? (a) Calculate the expected time and variance for each activity. Enter these values in the appropriate columns in the table above. (b) Which activities form the critical path? (c) What is the estimated time of the critical path? (d) What are the project variance and the project standard deviation? (e) What is the probability of completion of the project before week 42?

(Essay)
4.7/5
(77)

WBS stands for which of the following project management tools?

(Multiple Choice)
4.9/5
(71)

Which of the following statements regarding Gantt charts is TRUE?

(Multiple Choice)
4.8/5
(84)

In PERT analysis, the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.

(True/False)
4.7/5
(71)

Explain why the critical path is the longest, not the shortest, path through a network.

(Essay)
4.8/5
(78)
Showing 21 - 40 of 131