Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

If an activity whose normal duration is 15 days can be shortened to 11 days for an added cost of $2,000, what is the crash cost per period?

(Multiple Choice)
4.8/5
(87)

The control of projects involves close monitoring of which of the following?

(Multiple Choice)
4.8/5
(89)

A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=6.

(Multiple Choice)
4.7/5
(91)

The ________ is the computed longest time path(s) through a network.

(Short Answer)
4.9/5
(87)

A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or more?

(Multiple Choice)
4.7/5
(72)

The project organization works best when which of the following conditions are satisfied? I. Work tasks can be defined with a specific goal and deadline. II. The job is typical and familiar to the existing organization. III. The work contains interrelated tasks requiring specialized skills. IV. The project is temporary but unimportant to long-term organizational success. V. The project cuts across organizational lines.

(Multiple Choice)
4.8/5
(63)

Agile project management is a type of work breakdown structure (WBS).

(True/False)
4.9/5
(90)

Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .80 probability that the project will be completed before approximately day:

(Multiple Choice)
4.8/5
(80)

________ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.

(Short Answer)
4.9/5
(82)

The critical path for the network activities shown below is ________ with duration ________. The critical path for the network activities shown below is ________ with duration ________.

(Multiple Choice)
4.7/5
(82)

Project managers often use the waterfall approach when managing agile projects.

(True/False)
4.8/5
(78)
Showing 121 - 131 of 131
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)