Exam 3: Project Management
Exam 1: Operations and Productivity138 Questions
Exam 2: Operations Strategy in a Global Environment134 Questions
Exam 3: Project Management131 Questions
Exam 4: Forecasting148 Questions
Exam 5: Design of Goods and Services126 Questions
Exam 6: Managing Quality226 Questions
Exam 7: Process Strategies259 Questions
Exam 8: Location Strategies233 Questions
Exam 9: Human Resources, Job Design, and Work Measurement321 Questions
Exam 10: Supply Chain Management158 Questions
Exam 11: Inventory Management230 Questions
Exam 12: Aggregate Planning and Sop122 Questions
Exam 13: Material Requirements Planning Mrp and Erp133 Questions
Exam 14: Short-Term Scheduling124 Questions
Exam 15: Lean Operations122 Questions
Exam 16: Maintenance and Reliability119 Questions
Exam 17: Decision-Making Tools101 Questions
Exam 18: Linear Programming102 Questions
Exam 19: Transportation Models92 Questions
Exam 20: Waiting-Line Models126 Questions
Exam 21: Learning Curves114 Questions
Exam 22: Simulation78 Questions
Exam 23: Applying Analytics to Big Data in Operations Management61 Questions
Select questions type
Draw the AOA and AON networks for the following project and calculate the minimum project duration.

(Essay)
4.9/5
(93)
Which of these statements regarding time-cost tradeoffs in CPM networks is TRUE?
(Multiple Choice)
4.8/5
(92)
A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=5.
(Multiple Choice)
4.7/5
(70)
Which of the following statements regarding time-cost tradeoffs in CPM networks is FALSE?
(Multiple Choice)
4.8/5
(65)
Three critical path activities from the same critical path are candidates for crashing on a CPM network. Activity details are in the table below.
(a) What is the crash cost per unit time for activity A?
(b) What is the crash cost per unit time for activity B?
(c) Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
(d) Assuming no other paths become critical, which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
(e) Assuming no other paths become critical, how much can this project be shortened at what total added cost?
(Essay)
4.8/5
(77)
A(n) ________ is an organization formed to ensure that programs (projects) receive the proper management and attention.
(Short Answer)
4.9/5
(71)
Consider the network described in the table below.
(a) Calculate the expected duration of each activity.
(b) Calculate the expected duration and variance of the critical path.
(c) Calculate the probability that the project will be completed in more than 28 weeks time units.
(Essay)
5.0/5
(79)
Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
(a) What is the crash cost per unit time for each of the three activities?
(b) Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
(c) Assuming no other paths become critical, which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
(Essay)
4.9/5
(85)
A combination of effective Gantt chart use and other tactics allowed Delta to cut the average time for a plane layover by what % of the original 60-minute duration?
(Multiple Choice)
4.7/5
(93)
A project manager is interested in crashing a project with variable activity times. Which of the following tools should he/she employ?
(Multiple Choice)
4.9/5
(69)
The following activities are part of a project to be scheduled using the critical path method.
Calculate
(a) The critical path.
(b) The slack available at any non-critical points.
(c) The minimum project duration.
(Essay)
4.8/5
(72)
A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days. The sum of all activity variances is 81; the sum of variances along the critical path is 64. What is the probability that the project will take 130 or more days to complete?
(Multiple Choice)
4.9/5
(83)
The time an activity will take assuming very unfavorable conditions is:
(Multiple Choice)
4.9/5
(78)
Describe the differences between a Gantt chart and a PERT/CPM network.
(Essay)