Multiple Choice
Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost. 
A) One; $800
B) One; $6,800
C) Two; $500
D) Two; $5,000
E) One or Two should be crashed; $1,300