Exam 6: Lean Systems

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

With a batch size of 300 units,what is the capacity of process A as shown in Scenario 6.1?

(Multiple Choice)
4.8/5
(71)

Degan's Salad Dressings uses a Kanban system.The daily demand for corrugated boxes used in packaging its dressings is 300 boxes.The average waiting time for a container of boxes is 0.25 day.The processing time for a container of boxes is 0.1 day,and a container holds 10 boxes.If Burdell wishes to use a 10% policy variable,how many containers are needed?

(Essay)
4.9/5
(79)

The value stream mapping tool often requires completion of the future state drawing before the current state drawing,to help managers see the future state goals and more easily identify problems with the current state of the process.

(True/False)
4.7/5
(89)

A Kanban is a card used to control the flow of production in many just-in-time systems.

(True/False)
4.8/5
(75)

Continuous improvement with lean systems:

(Multiple Choice)
4.8/5
(75)

________ refers to the goal of having a setup time of fewer than 10 minutes.

(Essay)
5.0/5
(65)

Burdell Salad Dressings uses a Kanban system.The daily demand for corrugated boxes used in packaging its dressings is 300 boxes.The average waiting time for a container of boxes is 0.25 day.The processing time for a container of boxes is 0.1 day,and a container holds 10 boxes.If Burdell wishes to use a 5% policy variable,what is the level of work in process inventory in their plant?

(Essay)
4.8/5
(87)

When determining the number of kanban containers,discuss the impact of alpha,the policy variable,on the total amount of inventory in the system.If alpha is set equal to zero,is system inventory zero? What would be required to achieve a system-wide inventory of zero?

(Essay)
4.9/5
(70)

Briefly discuss the House of Toyota,including its origin and key points.

(Essay)
4.8/5
(75)

________ is the combining of parts or products with similar characteristics into families and setting aside groups of machines for their production.

(Essay)
4.9/5
(94)

The just-in-time (JIT)philosophy is the belief that cutting inventory and removing non-value-added activities in operations can eliminate waste.

(True/False)
4.8/5
(70)

Scenario 6.1 El Gran Raton,the producers of the finest carpincho wallets in all of Argentina,examined their production process in the form of a value stream map,displayed below. Scenario 6.1 El Gran Raton,the producers of the finest carpincho wallets in all of Argentina,examined their production process in the form of a value stream map,displayed below.   Daniel Penfield artist -Use Scenario 6.1 to determine the total production lead time for carpincho gloves. Daniel Penfield artist -Use Scenario 6.1 to determine the total production lead time for carpincho gloves.

(Multiple Choice)
4.8/5
(77)

What is schedule stability and why is it important in a lean system?

(Essay)
5.0/5
(75)

Case 6.2 The Jewel Golf Club Company,which recently began using a Kanban system,has had problems with high inventory levels of one of the handle grips used to make several versions of its clubs.Daily demand for the grip is 3000 units,average waiting time during production is 0.20 day,processing time is 0.10 day per container,and a container holds 150 grips. -Use the information in Case 6.2.How many Kanban containers would Jewel require if a 5% policy variable is used?

(Multiple Choice)
4.9/5
(91)

A firm that averages sales of 320 units for every 480-minute shift it runs has a takt time of 90 seconds.

(True/False)
5.0/5
(78)

In Scenario 6.1,what is the significance of the two jagged arrows leading from the box labeled Production Control to the boxes labeled Supplier and Customer?

(Multiple Choice)
4.9/5
(70)

Briefly outline the steps to be followed in evaluating and improving a process using value stream mapping.

(Essay)
4.9/5
(76)

In a lean system,large inventories are not considered a type of waste,because they prevent operator wait times.

(True/False)
4.9/5
(76)

When implementing a lean system:

(Multiple Choice)
4.9/5
(76)

With a batch size of 360 units,which process step in Scenario 6.1 is the bottleneck?

(Multiple Choice)
4.8/5
(90)