Exam 10: The Project Manager
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
The effective project manager is able to cope with constantly changing conditions.
(True/False)
4.9/5
(81)
To control the project, the project manager must track actual progress and compare it with planned progress.
(True/False)
4.8/5
(75)
Leadership requires that the project manager be highly motivated and set a positive example for the project team.
(True/False)
4.8/5
(90)
A final way in which the project manager can develop people is by having them attend formal training sessions.
(True/False)
4.9/5
(65)
involves selecting the project team members who are best qualified to perform each task and then empowering them to do it.
(Multiple Choice)
5.0/5
(79)
A project manager also needs good interpersonal skills to deal with disagreement or divisiveness among team
members.Such situations can require delicate handling on the project manager's part.
(True/False)
4.8/5
(69)
It is the responsibility of the to make sure that the customer is satisfied that the work scope is completed in a quality manner, within budget, and on time.
(Multiple Choice)
4.9/5
(91)
The project manager must be careful to create situations that cause individuals to become discouraged.
(True/False)
4.7/5
(83)
The project manager has the responsibility for in terms of specific results.
(Multiple Choice)
4.9/5
(73)
Effective communication establishes credibility and builds trust.
(True/False)
4.8/5
(92)
The project manager establishes ongoing communication with the customer to keep the customer at a distance and to determine whether there are any changes in expectations.
(True/False)
4.9/5
(85)
During the project life cycle, project managers encounter many occasions to employ their negotiating skills in interactions with the sponsor or customer, the project organization's management, subcontractors, vendors, and end users of the project's end product.
(True/False)
4.8/5
(84)
The project manager sets the tone for the project team by establishing an environment of trust, high expectations, and enjoyment.
(True/False)
4.8/5
(87)
Effective delegation requires that the project manager have
(Multiple Choice)
4.9/5
(86)
The spearheads development of a plan to achieve the project objective.
(Multiple Choice)
5.0/5
(80)
Interview project managers who have skills that you want to develop in yourself to develop the skills necessary to be an effective project manager.
(True/False)
4.8/5
(67)
The capable project manager understands what motivates team members and creates a competitive environment in which individuals compete as part of a high-performing team and are required to excel.
(True/False)
4.8/5
(65)
The one thing that you can be sure will happen during a project is
(Multiple Choice)
4.9/5
(82)