Exam 5: Developing the Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Latest finish time LF) is the latest time by which a specific activity must be

Free
(Multiple Choice)
4.7/5
(79)
Correct Answer:
Verified

B

As the project progresses, the actual finish times AFs) of completed activities will determine

Free
(Multiple Choice)
4.8/5
(69)
Correct Answer:
Verified

A

It is a good practice to have the person who will be responsible for performing a specific activity estimate the duration that other resources would need to complete that activity.

Free
(True/False)
4.9/5
(84)
Correct Answer:
Verified

False

Free slack is calculated by finding the lowest of the values of total slack for all the activities entering into a specific activity and then

(Multiple Choice)
5.0/5
(89)

With projects for which there is a high degree of uncertainty about the estimated durations for activities, it is possible to use three time estimates:

(Multiple Choice)
4.9/5
(96)

Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.

(Multiple Choice)
4.8/5
(84)

The development team develops, delivers, and demonstrates during a sprint.

(Multiple Choice)
4.9/5
(75)

The estimated duration for each activity is indicated by a bar spanning the period

(Multiple Choice)
4.9/5
(77)

Latest start time is calculated by

(Multiple Choice)
5.0/5
(89)

Throughout a project, changes may occur that have an impact on the schedule.

(True/False)
4.8/5
(70)

The latest finish time for a specific activity must be the same as or earlier than the earliest of all the latest start times of all the activities emerging directly from that specific activity.

(True/False)
4.9/5
(73)

Earliest finish time EF) is the earliest time by which a specific activity can be completed, calculated

(Multiple Choice)
4.8/5
(65)

The estimated types and quantities of resources required for an activity together with the availability of those resources will influence the

(Multiple Choice)
4.9/5
(87)

The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and

(Multiple Choice)
4.8/5
(83)

Negative slack indicates a lack of slack over the entire project and the amount of time

(Multiple Choice)
4.9/5
(82)

The estimated duration for each activity must be the total elapsed time,

(Multiple Choice)
4.8/5
(74)

People sometimes perform to expectations, their effort will expand to fill the whole number of scheduled days allotted,

(Multiple Choice)
4.9/5
(75)

When the customer requests a change, the contractor or project team should estimate the impact on the project schedule and budget and then go ahead with the work without customer approval.

(True/False)
4.7/5
(78)

Schedule control involves four steps.List the four steps in order.

(Short Answer)
4.7/5
(75)

A consistent time base, such as hours or days or weeks, should be used for all the estimated durations of activities in a network diagram.

(True/False)
4.8/5
(87)