Exam 7: Determining Costs, Budget, and Earned Value
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
The is the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time.
Free
(Multiple Choice)
4.8/5
(93)
Correct Answer:
C
At the beginning of the project, it may not be possible to estimate the costs for all activities with a level of confidence regarding their accuracy.This is especially true for
Free
(Multiple Choice)
4.7/5
(76)
Correct Answer:
B
A cost is determined for each period, based on when the activities that make up the work package are scheduled to be performed, to create
(Multiple Choice)
4.9/5
(87)
It's crucial that cost variances and inefficiencies be identified early so that
(Multiple Choice)
4.7/5
(85)
Another indicator of cost performance is cost variance CV).If the cumulative earned value is greater than the cumulative actual costs, then
(Multiple Choice)
4.9/5
(87)
Cumulative actual cost CAC) should be calculated to compare to the cumulative budgeted cost CBC).
(True/False)
4.9/5
(86)
Contingency costs in the project costs estimate, also referred to as , are to cover unexpected situations that may come up during the project, such as items that may have been overlooked when the initial project scope was defined, activities that may have to be redone because they may not work the first time redesigns), or a high probability or high impact risk that may occur.
(Multiple Choice)
4.7/5
(91)
The is the amount that was actually spent to accomplish the work that was scheduled to be performed up to that point in time.
(Multiple Choice)
4.8/5
(74)
Calculate the forecasted cost at completion if the total budgeted cost is $15,000, the cumulative actual cost is $10,000, and the cumulative earned value is $12,000.
(Multiple Choice)
4.9/5
(87)
Which of the following is not a way to reduce the costs of activities:
(Multiple Choice)
4.8/5
(93)
Materials costs in the project costs estimate are the estimated costs of materials that the project team or contractor
(Multiple Choice)
4.8/5
(73)
Large projects would have charge codes for the work package numbers to
(Multiple Choice)
5.0/5
(80)
The is the product of the percent complete and the sum of the estimated costs of all the specific activities that make up a work package or the project.
(Multiple Choice)
4.7/5
(84)
Calculate the forecasted cost at completion if the total budgeted cost = $10,000, the CEV is $8,000, and the CAC is $4,000.
(Multiple Choice)
4.9/5
(80)
There are two approaches to establishing the total budgeted cost for each work package:
(Multiple Choice)
4.8/5
(80)