Exam 7: Determining Costs, Budget, and Earned Value

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The budget for each work package is

Free
(Multiple Choice)
4.9/5
(68)
Correct Answer:
Verified

C

The is the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time.

Free
(Multiple Choice)
4.8/5
(93)
Correct Answer:
Verified

C

At the beginning of the project, it may not be possible to estimate the costs for all activities with a level of confidence regarding their accuracy.This is especially true for

Free
(Multiple Choice)
4.7/5
(76)
Correct Answer:
Verified

B

Facilities costs in the project costs estimate are for

(Multiple Choice)
4.8/5
(75)

A cost is determined for each period, based on when the activities that make up the work package are scheduled to be performed, to create

(Multiple Choice)
4.9/5
(87)

Travel costs in the project costs estimate are for

(Multiple Choice)
4.7/5
(77)

It's crucial that cost variances and inefficiencies be identified early so that

(Multiple Choice)
4.7/5
(85)

Another indicator of cost performance is cost variance CV).If the cumulative earned value is greater than the cumulative actual costs, then

(Multiple Choice)
4.9/5
(87)

Committed costs are also known as discharged or postponed costs.

(True/False)
4.9/5
(71)

Cumulative actual cost CAC) should be calculated to compare to the cumulative budgeted cost CBC).

(True/False)
4.9/5
(86)

Contingency costs in the project costs estimate, also referred to as , are to cover unexpected situations that may come up during the project, such as items that may have been overlooked when the initial project scope was defined, activities that may have to be redone because they may not work the first time redesigns), or a high probability or high impact risk that may occur.

(Multiple Choice)
4.7/5
(91)

The is the amount that was actually spent to accomplish the work that was scheduled to be performed up to that point in time.

(Multiple Choice)
4.8/5
(74)

Calculate the forecasted cost at completion if the total budgeted cost is $15,000, the cumulative actual cost is $10,000, and the cumulative earned value is $12,000.

(Multiple Choice)
4.9/5
(87)

Which of the following is not a way to reduce the costs of activities:

(Multiple Choice)
4.8/5
(93)

It is important to manage the cash flow on a project.

(True/False)
4.9/5
(80)

Materials costs in the project costs estimate are the estimated costs of materials that the project team or contractor

(Multiple Choice)
4.8/5
(73)

Large projects would have charge codes for the work package numbers to

(Multiple Choice)
5.0/5
(80)

The is the product of the percent complete and the sum of the estimated costs of all the specific activities that make up a work package or the project.

(Multiple Choice)
4.7/5
(84)

Calculate the forecasted cost at completion if the total budgeted cost = $10,000, the CEV is $8,000, and the CAC is $4,000.

(Multiple Choice)
4.9/5
(80)

There are two approaches to establishing the total budgeted cost for each work package:

(Multiple Choice)
4.8/5
(80)