Exam 7: Determining Costs, Budget, and Earned Value
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
If you put off corrective actions until some point in the distant future, the negative cost variance may deteriorate in the project.
(True/False)
5.0/5
(81)
It is important to use the as the standard against which actual cost is compared.
(Multiple Choice)
4.7/5
(78)
Managing cash flow involves making sure that sufficient payments are received from the customer in time so that
(Multiple Choice)
4.8/5
(90)
The is the amount that was budgeted to accomplish the work that was schedule to be performed up to that point in time.
(Multiple Choice)
4.8/5
(79)
Determining the earned value involves collecting data on the percent complete for each work package and then converting this percentage to a dollar amount by multiplying the of the work package by the percent complete.
(Multiple Choice)
4.9/5
(92)
Based on analysis of actual cost it is possible to forecast what the total costs will be at the completion of the project or work package.
(True/False)
4.7/5
(79)
involves the following: Analyzing cost performance to determine which work packages may require corrective action; Deciding what specific corrective action should be taken; and Revising the project plan, including time and cost estimates, to incorporate the planned corrective action.
(Multiple Choice)
4.8/5
(80)
Once a total budgeted cost has been established for each work package, the second step in the project budgeting process is to
(Multiple Choice)
4.9/5
(82)
In many cases, there will be a tradeoff, reducing cost variances will involve a reduction in project scope or a delay in the project schedule.
(True/False)
4.9/5
(74)
The contractor might try to negotiate payment terms that require the customer to do one or more of the following except
(Multiple Choice)
4.7/5
(85)
It's important that the person estimating the percent complete not only assess how much work has been performed but also consider
(Multiple Choice)
4.8/5
(72)
The total project cost is often estimated during the phase of the project or when the project charter or a proposal is prepared
(Multiple Choice)
4.9/5
(62)
As data are collected on , including portions of any committed cost, they need to be totaled by work package so that they can be compared to the
(Multiple Choice)
4.8/5
(85)
Equipment costs in the project costs estimate are for equipment
(Multiple Choice)
4.8/5
(87)
The is the sum of the estimated costs of all the specific activities that make up a work package or the project.
(Multiple Choice)
4.8/5
(92)
Calculate the cost variance if the cumulative earned value is $10 and the cumulative actual costs are $20.
(Multiple Choice)
4.8/5
(96)
The key to effective cost control is waiting to address negative cost variances and cost inefficiencies after they are identified.
(True/False)
4.8/5
(87)
Committed costs need to be treated in a special way so that the system
(Multiple Choice)
4.9/5
(77)