If you put off corrective actions until some point in the distant future, the negative cost variance may deteriorate in the project.

(True/False)
5.0/5
(81)

It is important to use the as the standard against which actual cost is compared.

(Multiple Choice)
4.7/5
(78)

Managing cash flow involves making sure that sufficient payments are received from the customer in time so that

(Multiple Choice)
4.8/5
(90)

Cost estimates should be unreasonable and excessive.

(True/False)
4.8/5
(82)

The is the amount that was budgeted to accomplish the work that was schedule to be performed up to that point in time.

(Multiple Choice)
4.8/5
(79)

Determining the earned value involves collecting data on the percent complete for each work package and then converting this percentage to a dollar amount by multiplying the of the work package by the percent complete.

(Multiple Choice)
4.9/5
(92)

Based on analysis of actual cost it is possible to forecast what the total costs will be at the completion of the project or work package.

(True/False)
4.7/5
(79)

involves the following: Analyzing cost performance to determine which work packages may require corrective action; Deciding what specific corrective action should be taken; and Revising the project plan, including time and cost estimates, to incorporate the planned corrective action.

(Multiple Choice)
4.8/5
(80)

Once a total budgeted cost has been established for each work package, the second step in the project budgeting process is to

(Multiple Choice)
4.9/5
(82)

In many cases, there will be a tradeoff, reducing cost variances will involve a reduction in project scope or a delay in the project schedule.

(True/False)
4.9/5
(74)

The contractor might try to negotiate payment terms that require the customer to do one or more of the following except

(Multiple Choice)
4.7/5
(85)

It's important that the person estimating the percent complete not only assess how much work has been performed but also consider

(Multiple Choice)
4.8/5
(72)

The total project cost is often estimated during the phase of the project or when the project charter or a proposal is prepared

(Multiple Choice)
4.9/5
(62)

When the budgets for all the work packages are summed,

(Multiple Choice)
4.9/5
(72)

As data are collected on , including portions of any committed cost, they need to be totaled by work package so that they can be compared to the

(Multiple Choice)
4.8/5
(85)

Equipment costs in the project costs estimate are for equipment

(Multiple Choice)
4.8/5
(87)

The is the sum of the estimated costs of all the specific activities that make up a work package or the project.

(Multiple Choice)
4.8/5
(92)

Calculate the cost variance if the cumulative earned value is $10 and the cumulative actual costs are $20.

(Multiple Choice)
4.8/5
(96)

The key to effective cost control is waiting to address negative cost variances and cost inefficiencies after they are identified.

(True/False)
4.8/5
(87)

Committed costs need to be treated in a special way so that the system

(Multiple Choice)
4.9/5
(77)