Exam 5: Projects
Exam 1: Operations and Supply Chain Management84 Questions
Exam 2: Strategy and Sustainability54 Questions
Exam 3: Forecasting101 Questions
Exam 4: Strategic Capacity Management64 Questions
Exam 5: Projects77 Questions
Exam 6: Manufacturing and Service Processes73 Questions
Exam 7: Service Processes85 Questions
Exam 8: Sales and Operations Planning65 Questions
Exam 9: Material Requirements Planning89 Questions
Exam 10: Quality Management and Six Sigma149 Questions
Exam 11: Inventory Management108 Questions
Exam 12: Lean Supply Chains73 Questions
Exam 13: Global Sourcing and Procurement78 Questions
Exam 14: Location, Logistics, and Distribution61 Questions
Select questions type
In a CPM analysis if you subtract the late finish from the early finish the result is the activity's slack time.
(True/False)
4.9/5
(75)
The valuations in an Earned Value Management analysis must be either profits or revenue.
(True/False)
4.8/5
(76)
One of the assumptions made using CPM is that project activity sequence relationships can be specified and networked.
(True/False)
4.8/5
(77)
You have the following time and cost information below for use in a Time-Cost CPM Scheduling model. Activity Normal Time Crash Time Normal Cost Crash Cost A 3 2 \ 400 \ 600 B 5 3 \ 600 \ 1200 C 4 1 \ 300 \ 1500
What are the three costs per unit of time to expedite each activity?
(Multiple Choice)
4.9/5
(76)
A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?
(Multiple Choice)
5.0/5
(77)
The critical path in a CPM analysis is always the shortest path through the network.
(True/False)
4.9/5
(77)
The fact that organizations are flattening is one of the reasons that project management is important.
(True/False)
4.9/5
(64)
A company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below: Immediate Activity Designation Predecessor Time in Days Break down both machines A None 3 Clean machine 1 B A 3 Clean machine 2 C A 3 Re-set machine 1 D B 4 Re-set machine 2 E C 2 Re-calibrate both machines F D and E 1 Final test G F 1
Using CPM,which activities have slack in this project?
(Multiple Choice)
4.7/5
(87)
What are "project milestones?" _________________________________________
(Short Answer)
4.8/5
(93)
A company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below: Immediate Activity Designation Predecessor Time in Days Break down both machines A None 3 Clean machine 1 B A 3 Clean machine 2 C A 3 Re-set machine 1 D B 4 Re-set machine 2 E C 2 Re-calibrate both machines F D and E 1 Final test G F 2
Using CPM,which activities make up the critical path?
(Multiple Choice)
4.9/5
(87)
The project indirect costs associated with a project include overhead,facilities,and resource opportunity costs.
(True/False)
4.8/5
(76)
The critical path in a project is that sequence of activities that consume the longest amount of time in a project network of activities.
(True/False)
4.8/5
(76)
You know when you have arrived at the optimal solution in using the Time-Cost CPM Scheduling model analysis when what happens?
(Multiple Choice)
4.8/5
(84)
Breakthrough projects are those that provide fundamental improvements to existing products.
(True/False)
4.9/5
(79)
One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points.
(True/False)
4.7/5
(91)
Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost Cost A None 3 2 \ 200 \ 400 B A 4 3 \ 300 \ 600 C A 1 1 \ 300 \ 300 D B and C 3 2 \ 500 \ 550 E D 2 1 \ 500 \ 900
If you crash this project to reduce the total time by four days,what is the total time of the project and total cost? __________________
(Essay)
4.8/5
(86)
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost (Direct) Cost (Direct) A None 3 2 \ 300 \ 400 B A 3 3 \ 100 \ 100 C A 1 1 \ 200 \ 200 D B and C 3 2 \ 400 \ 550 E D 2 1 \ 500 \ 900 F E 3 3 \ 200 \ 200 G F 2 2 \ 100 \ 100
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect)project cost? ____________________
(Essay)
4.8/5
(71)
Showing 61 - 77 of 77