In a CPM analysis if you subtract the late finish from the early finish the result is the activity's slack time.

(True/False)
4.9/5
(75)

The valuations in an Earned Value Management analysis must be either profits or revenue.

(True/False)
4.8/5
(76)

One of the assumptions made using CPM is that project activity sequence relationships can be specified and networked.

(True/False)
4.8/5
(77)

You have the following time and cost information below for use in a Time-Cost CPM Scheduling model. Activity Normal Time Crash Time Normal Cost Crash Cost A 3 2 \ 400 \ 600 B 5 3 \ 600 \ 1200 C 4 1 \ 300 \ 1500 What are the three costs per unit of time to expedite each activity?

(Multiple Choice)
4.9/5
(76)

A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?

(Multiple Choice)
5.0/5
(77)

The critical path in a CPM analysis is always the shortest path through the network.

(True/False)
4.9/5
(77)

The fact that organizations are flattening is one of the reasons that project management is important.

(True/False)
4.9/5
(64)

A company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below: Immediate Activity Designation Predecessor Time in Days Break down both machines A None 3 Clean machine 1 B A 3 Clean machine 2 C A 3 Re-set machine 1 D B 4 Re-set machine 2 E C 2 Re-calibrate both machines F D and E 1 Final test G F 1 Using CPM,which activities have slack in this project?

(Multiple Choice)
4.7/5
(87)

What are "project milestones?" _________________________________________

(Short Answer)
4.8/5
(93)

A company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below: Immediate Activity Designation Predecessor Time in Days Break down both machines A None 3 Clean machine 1 B A 3 Clean machine 2 C A 3 Re-set machine 1 D B 4 Re-set machine 2 E C 2 Re-calibrate both machines F D and E 1 Final test G F 2 Using CPM,which activities make up the critical path?

(Multiple Choice)
4.9/5
(87)

The project indirect costs associated with a project include overhead,facilities,and resource opportunity costs.

(True/False)
4.8/5
(76)

The critical path in a project is that sequence of activities that consume the longest amount of time in a project network of activities.

(True/False)
4.8/5
(76)

You know when you have arrived at the optimal solution in using the Time-Cost CPM Scheduling model analysis when what happens?

(Multiple Choice)
4.8/5
(84)

Breakthrough projects are those that provide fundamental improvements to existing products.

(True/False)
4.9/5
(79)

One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points.

(True/False)
4.7/5
(91)

Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost Cost A None 3 2 \ 200 \ 400 B A 4 3 \ 300 \ 600 C A 1 1 \ 300 \ 300 D B and C 3 2 \ 500 \ 550 E D 2 1 \ 500 \ 900 If you crash this project to reduce the total time by four days,what is the total time of the project and total cost? __________________

(Essay)
4.8/5
(86)

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost (Direct) Cost (Direct) A None 3 2 \ 300 \ 400 B A 3 3 \ 100 \ 100 C A 1 1 \ 200 \ 200 D B and C 3 2 \ 400 \ 550 E D 2 1 \ 500 \ 900 F E 3 3 \ 200 \ 200 G F 2 2 \ 100 \ 100 The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect)project cost? ____________________

(Essay)
4.8/5
(71)