You have the following time and cost information below for use in a Time-Cost CPM Scheduling model.
What are the three costs per unit of time to expedite each activity?
A) A=$300,B=$200,C=$300
B) A=$100,B=$200,C=$400
C) A=$200,B=$200,C=$200
D) A=$100,B=$400,C=$300
E) A=$200,B=$300,C=$400