Earned Value Management (EVM)is a technique for measuring project progress in an objective manner.

(True/False)
4.8/5
(87)

In CPM the late start time estimate is the latest time you can start an activity and still keep the entire project on schedule.

(True/False)
5.0/5
(86)

A company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below: Immediate Activity Designation Predecessor Time in Days Break down both machines A None 3 Clean machine 1 B A 3 Clean machine 2 C A 3 Re-set machine 1 D B 1 Re-set machine 2 E C 2 Re-calibrate both machines F D and E 1 Final test G F 2 Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project)?

(Multiple Choice)
4.7/5
(76)

You have been placed in charge of a large project.Shortened communication lines are required to insure quick resolution of problems as they arise.You recognize that the project is going to take a lot of time and require a lot of team pride,motivation,and commitment by all members.Which project management structure should you use in this situation?

(Multiple Choice)
4.8/5
(89)

A project can be subdivided into which of the following?

(Multiple Choice)
4.9/5
(72)

For an activity in a CPM analysis the Early Finish time is 20 and the Late Finish time is 20.Which of the following statements is true?

(Multiple Choice)
4.9/5
(88)

What is the criterion for determining whether a project activity is on the "critical path" or not?

(Essay)
4.8/5
(79)

In CPM analysis it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?

(Multiple Choice)
4.8/5
(81)

The second step in managing a project is writing the Statement of Work.

(True/False)
4.9/5
(59)

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below. Immediate Normal Crash Normal Crash Activity Immediate Time Time Cost (Direct) Cost (Direct) A None 3 2 \ 300 \ 400 B A 3 3 \ 100 \ 100 C A 1 1 \ 200 \ 200 D B and C 3 2 \ 400 \ 550 E D 2 1 \ 500 \ 900 F E 3 3 \ 200 \ 200 G F 2 2 \ 100 \ 100 The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs)?

(Multiple Choice)
4.7/5
(71)

For an activity in a CPM analysis,the Early Start time is 8 and the Late Start time is 10.Which of the following statements is true?

(Multiple Choice)
4.9/5
(81)

Project management can be defined as planning,directing,and controlling resources to meet the technical,cost,and time constraints of the project.

(True/False)
4.8/5
(75)

A simple project listing of five activities,their predecessors and their respective time estimates are presented below: Activity Immediate Predecessor Time in Days A None 2 B A 2 C A 1 D B and C 3 E D 1 Using the CPM,which activities have slack in this project?

(Multiple Choice)
4.8/5
(89)

Derivative projects are those which address incremental changes to products or processes.

(True/False)
4.8/5
(77)

Project management software available today combines CPM and other scheduling aids,like Gantt charting,to aid in tracking progress of project completion.

(True/False)
4.9/5
(83)

Which of the following is a graphic project report used in project management?

(Multiple Choice)
4.8/5
(87)

Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost Cost A None 3 2 \ 200 \ 400 B A 4 3 \ 300 \ 600 C A 1 1 \ 300 \ 300 D B and C 3 2 \ 500 \ 550 E D 2 1 \ 500 \ 900 If you crash this project to reduce the total time by one day what is the total time of the project and total cost?

(Multiple Choice)
4.7/5
(82)

Describe how CPM handles the trade-offs between time and cost in the scheduling of a project.

(Essay)
4.8/5
(92)

A matrix project attempts to blend properties of functional and pure project structures.

(True/False)
4.8/5
(77)

You are managing a project and need to cut the cost of the project.You decide to transfer workers to another job to cut the project's costs.Costs associated with transferring the workers are an example of project indirect costs.

(True/False)
4.8/5
(75)
Showing 41 - 60 of 77