Exam 5: Stakeholder Analysis and Communication Planning
Exam 1: Introduction to Project Management49 Questions
Exam 2: Project Selection and Prioritization52 Questions
Exam 3: Organizational Capability: Structure,Culture and Roles50 Questions
Exam 4: Chartering Projects39 Questions
Exam 5: Stakeholder Analysis and Communication Planning46 Questions
Exam 6: Defining Scope and Constructing Work Breakdown Structures WBS44 Questions
Exam 7: Scheduling Activities56 Questions
Exam 8: Resourcing Projects45 Questions
Exam 9: Budgeting Projects46 Questions
Exam 10: Project Risk Planning45 Questions
Exam 11: Project Quality Planning and Project Kick-Off45 Questions
Exam 12: Project Supply Chain Management45 Questions
Exam 13: Leading and Managing Project Teams46 Questions
Exam 14: Determining Project Progress and Results44 Questions
Exam 15: Finishing the Project30 Questions
Select questions type
The plan-do-check-act model used to improve processes is also an effective model that project managers can use to improve project meetings.
Free
(True/False)
4.8/5
(85)
Correct Answer:
True
The primary output of the "Identify Stakeholders" process is the project communications plan.
Free
(True/False)
4.8/5
(93)
Correct Answer:
False
While expensive,it is often advisable for virtual team members who live across the globe to meet face-to-face at least once,especially early in the project.
Free
(True/False)
4.8/5
(70)
Correct Answer:
True
By identifying stakeholders and their needs,project managers can be more effective in all the following ways EXCEPT:
(Multiple Choice)
4.8/5
(82)
Plan Communications is the process of developing an appropriate approach and plan for project communications based on stakeholders' information needs and requirements and available organizational assets.
(True/False)
4.9/5
(82)
Establishing a positive relationship with all key stakeholders early in the project helps to create a desire among those stakeholders to support the project,and builds the communications foundation for the project.
(True/False)
4.7/5
(81)
Project management plans generally include all of the following elements EXCEPT:
(Multiple Choice)
4.9/5
(74)
A point or matter in question or in dispute,not settled or over which there are opposing views or disagreements is called a(n)_____:
(Multiple Choice)
4.8/5
(81)
The communications management plan is finalized during project planning,and should only be changed through a formal change control process.
(True/False)
4.7/5
(85)
Describe the approach you would use to build relationships with key external stakeholders.
(Essay)
4.9/5
(78)
A project communications management plan generally includes all of the following information EXCEPT:
(Multiple Choice)
4.8/5
(62)
A virtual team is a group of persons with a shared goal,who fulfill their roles largely through face-to-face communications.
(True/False)
4.8/5
(76)
Project relationship building activities include encouraging open communications and using shared learning.
(True/False)
4.8/5
(83)
Project stakeholders can be prioritized based on a number of factors,including one of the following:
(Multiple Choice)
4.7/5
(77)
In order to plan for a project meeting,project managers should develop an agenda.All of the following statements accurately describe the development and use of a project meeting agenda EXCEPT:
(Multiple Choice)
4.8/5
(90)
Which of these is not one of the primary types of information captured in a project meeting?
(Multiple Choice)
4.9/5
(67)
Contemporary project communications typically include both push methods such as blogs,and pull methods such as voice mail.
(True/False)
4.9/5
(86)
In the project communications matrix,all of the following "who" items are typically included EXCEPT:
(Multiple Choice)
4.9/5
(66)
A project communications matrix includes all of the following information EXCEPT:
(Multiple Choice)
5.0/5
(80)