Exam 11: Project Quality Planning and Project Kick-Off

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following quality management thought leaders is generally credited with contributing the insight that team learning is necessary to improve quality?

Free
(Multiple Choice)
4.9/5
(70)
Correct Answer:
Verified

B

All of the following items are valid reasons to conduct a project kick-off meeting EXCEPT:

Free
(Multiple Choice)
4.7/5
(77)
Correct Answer:
Verified

D

Project stakeholders will judge the quality of project work processes as well as project deliverables.

Free
(True/False)
5.0/5
(65)
Correct Answer:
Verified

True

A high level view of processes and stakeholders,that starts with suppliers and ends with customers,is sometimes referred to as a "Plan-Do-Check-Act" (PDCA)model.

(True/False)
4.9/5
(79)

Fact-based management includes four key ideas.Which of the following is among the key ideas associated with fact-based management?

(Multiple Choice)
4.9/5
(67)

A source of variation that is inherent in a system and predictable is typically known as:

(Multiple Choice)
4.8/5
(71)

The outputs of Control Quality may include recommended preventive actions designed to ensure the future performance of project work is aligned with the project management plan.

(True/False)
4.8/5
(75)

All of the following reasons explain why it is better to design quality into processes than to find problems through inspections EXCEPT:

(Multiple Choice)
5.0/5
(70)

W.Edwards Deming asserted that managers need to understand both serial variation and sequential variation and then work to reduce both.

(True/False)
4.7/5
(77)

W.Edwards Deming argued that managers must understand cause and effect relationships to predict future behavior.

(True/False)
4.8/5
(79)

All of the following items contribute to developing empowered performance in an organization EXCEPT:

(Multiple Choice)
4.8/5
(74)

The quality management plan describes how an organization's quality policies will be implemented.

(True/False)
4.9/5
(87)

During which DMAIC phase would you find the objectives of identify possible root causes,collect data,and confirm root causes through data analysis?

(Multiple Choice)
4.9/5
(82)

The purpose of process control is to be able to have confidence that outputs are predictable.

(True/False)
4.8/5
(82)

If necessary,the quality policy on a specific project may violate either the quality policies of the parent organization or of a major customer.

(True/False)
4.7/5
(71)

DMAIC is typically used as a method of implementing continuous improvement and can thus be practiced repeatedly.

(True/False)
4.7/5
(82)

Which of the following activities are typically included in a project kick-off meeting?

(Multiple Choice)
4.8/5
(89)

Assume you have been selected to lead your team in the development of a quality management plan.Identify and describe several components that a quality management plan should contain.

(Essay)
4.9/5
(88)

The goal of empowered performance is to improve performance results each and every period.

(True/False)
4.8/5
(85)

Perform Quality Assurance is the process of auditing the quality requirements,and the results from quality control measurements to ensure appropriate quality standards and operational definitions are used.

(True/False)
4.9/5
(84)
Showing 1 - 20 of 45