In the probabilistic approach to project network analysis, the time estimate annotated tm for any activity is the:

(Multiple Choice)
4.8/5
(70)

The latest starting time for an activity is equal to the latest finish time minus the activity time.

(True/False)
4.8/5
(78)

Concerning PERT and CPM:

(Multiple Choice)
4.8/5
(72)

A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:

(Multiple Choice)
4.9/5
(69)

A project is represented by the following diagram: A project is represented by the following diagram:   The expected duration of this project is: The expected duration of this project is:

(Multiple Choice)
4.9/5
(81)

The main function of dummy activities is to clarify relationships in network diagrams.

(True/False)
4.8/5
(91)

The network diagram shows sequential relationships among major activities on a project.

(True/False)
4.9/5
(93)

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is:

(Multiple Choice)
4.8/5
(101)

Which of the following is not one of the six key decisions in project management? (I) Selecting the project team (II) Deciding on the project manager's title (III) Managing and controlling project resources (IV) Deciding which projects to implement (V) Selecting the project manager

(Multiple Choice)
4.8/5
(84)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity D? What is the estimated slack time for activity D?

(Multiple Choice)
4.9/5
(71)

The advantage a precedence diagram has over a Gantt chart is:

(Multiple Choice)
4.8/5
(81)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity W? What is the estimated slack time for activity W?

(Multiple Choice)
4.9/5
(85)

A project is represented by the following diagram: A project is represented by the following diagram:   The critical path for the network shown is: The critical path for the network shown is:

(Multiple Choice)
4.8/5
(78)

Path probabilities are calculated by dividing path mean by path standard deviations.

(True/False)
4.9/5
(94)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity A? What is the estimated slack time for activity A?

(Multiple Choice)
4.9/5
(71)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity D? What is the estimated standard deviation in the time for activity D?

(Multiple Choice)
4.9/5
(74)

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23? What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23?

(Multiple Choice)
4.9/5
(78)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.9/5
(81)

A disadvantage of activity-on-node diagrams is the occasional need for dummy activities.

(True/False)
4.9/5
(83)

At which point does crashing of a project cease?