A project is represented by the following diagram: 
The critical path for the network shown is:
A) 1-3-6-7.
B) 1-2-4-7.
C) 1-4-7.
D) 1-3-4-7.
E) 1-2-5-7.
Correct Answer:

Verified
Correct Answer:
Verified