Exam 7: Project Management
Exam 1: Using Operations to Create Value115 Questions
Exam 2: Process Strategy and Analysis239 Questions
Exam 3: Quality and Performance198 Questions
Exam 4: Capacity Planning120 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems166 Questions
Exam 7: Project Management139 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management205 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning124 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration120 Questions
Exam 15: Supply Chain Sustainability78 Questions
Exam 16: Supplement A Decision Making107 Questions
Exam 17: Supplement J Operations Scheduling123 Questions
Exam 18: Supplement K Layout39 Questions
Exam 19: Supplement B Waiting Lines111 Questions
Exam 20: Supplement C Special Inventory Models53 Questions
Exam 21: Supplement D Linear Programming87 Questions
Exam 22: Supplement E Simulation54 Questions
Exam 23: Supplement F Financial Analysis55 Questions
Exam 24: Supplement G Acceptance Sampling Plans87 Questions
Exam 25: Supplement H Measuring Output Rates108 Questions
Exam 26: Supplement I Learning Curve Analysis50 Questions
Select questions type
A(n) ________ is an interrelated set of activities that has a definite starting and ending point and that results in a unique outcome for a specific allocation of resources.
(Short Answer)
4.7/5
(68)
To calculate the probability of completing a project by a certain date:
(Multiple Choice)
4.9/5
(78)
You are given the following information about activity F:
What is the normal cost for activity F?
(Multiple Choice)
4.9/5
(78)
Table 7.5
-Using Table 7.5, how many days can activity C be delayed without changing the whole project's earliest completion time?
(Multiple Choice)
4.8/5
(78)
A relationship that determines the sequence for undertaking activities is a precedence relationship.
(True/False)
4.8/5
(95)
Figure to accompany Table 7.7
Table 7.7
-What is the crashing cost per week for activity F in Table 7.7?
(Multiple Choice)
5.0/5
(62)
The savvy project manager knew there would be a high demand for finish carpenters in late October, so she started a crew early on one section of the house so they would be available to help elsewhere later on. This project manager is engaging in:
(Multiple Choice)
4.8/5
(75)
A project has three paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is True?
(Multiple Choice)
4.8/5
(75)
Table 7.9
-Using Table 7.9, what is the difference, in dollars, between the minimum-time schedule and the schedule created by crashing all activities to their limits? Assume that there are no indirect or penalty costs.
(Multiple Choice)
4.7/5
(90)
Figure to accompany Table 7.7
Table 7.7
-What is the critical path for the project shown in the above network and Table 7.7, using the normal times?
(Multiple Choice)
4.8/5
(84)
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks).
-Using Table 7.14, what is the critical path and expected completion time for this project?
(Multiple Choice)
4.9/5
(79)
A good risk management plan will contain which of these elements?
(Multiple Choice)
4.8/5
(88)
Table 7.4
-Using Table 7.4, what is the early start time for activity D?
(Multiple Choice)
4.8/5
(80)
Table 7.5
-Using Table 7.5, what is the earliest completion time of this project?
(Multiple Choice)
4.7/5
(89)
In making an estimate of the most pessimistic time for an activity, a manager deliberately estimates this time too high (i.e., longer than it should be). What is the result of this action, assuming the beta distribution is being used to make time estimates?
(Multiple Choice)
4.8/5
(75)
Table 7.6
-Using Table 7.6, suppose activity D can be shortened from four days to one day. Assume all other activity times remain the same. How much shorter will the total project earliest completion time become?
(Multiple Choice)
4.8/5
(78)
Table 7.10
Four possible options exist to crash activities: crash A by one week at a cost of $6,000; crash C by two weeks at a cost of $15,000; crash E by one week at a cost of $2,000; and crash I one week at a cost of $7,000. What is the maximum amount of additional profit that can be made by crashing an option (or options)?
A) less than or equal to $4,000
B) greater than $4,000 but less than or equal to $8,000
C) greater than $8,000 but less than or equal to $12,000
D) greater than $12,000
-If a project has exactly one critical path, which of the following statements is True?
(Multiple Choice)
4.9/5
(83)
Table 7.4
-Using Table 7.4, what is the latest finish time for activity C?
(Multiple Choice)
4.9/5
(66)