Multiple Choice
Figure to accompany Table 7.7
Table 7.7

-What is the critical path for the project shown in the above network and Table 7.7, using the normal times?
A) A-B-D-F
B) A-C-D-F
C) A-C-E-F
D) A-B-C-D-E-F
Correct Answer:

Verified
Correct Answer:
Verified