Exam 7: Project Management
Exam 1: Using Operations to Create Value115 Questions
Exam 2: Process Strategy and Analysis239 Questions
Exam 3: Quality and Performance198 Questions
Exam 4: Capacity Planning120 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems166 Questions
Exam 7: Project Management139 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management205 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning124 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration120 Questions
Exam 15: Supply Chain Sustainability78 Questions
Exam 16: Supplement A Decision Making107 Questions
Exam 17: Supplement J Operations Scheduling123 Questions
Exam 18: Supplement K Layout39 Questions
Exam 19: Supplement B Waiting Lines111 Questions
Exam 20: Supplement C Special Inventory Models53 Questions
Exam 21: Supplement D Linear Programming87 Questions
Exam 22: Supplement E Simulation54 Questions
Exam 23: Supplement F Financial Analysis55 Questions
Exam 24: Supplement G Acceptance Sampling Plans87 Questions
Exam 25: Supplement H Measuring Output Rates108 Questions
Exam 26: Supplement I Learning Curve Analysis50 Questions
Select questions type
Information accuracy relative to the completeness of the work breakdown structure and communication of timely information affect the:
(Multiple Choice)
4.7/5
(67)
Table 7.4
-Using Table 7.4, what is the earliest completion time for this project?
(Multiple Choice)
4.8/5
(93)
Table 7.6
-Using Table 7.6, suppose activity I is delayed, taking eight days to complete instead of two days. Assume all other activity times remain the same. How much longer will the total project earliest completion time become?
(Multiple Choice)
4.9/5
(80)
Table 7.13
All activity times for the project are in weeks.
-Using Table 7.13, what is the critical path of this project?
(Multiple Choice)
4.8/5
(86)
The phase of project management that takes the most resources is the ________, during which managers focus on activities that pertain to deliverables.
(Short Answer)
4.7/5
(90)
________ is the maximum length of time that an activity can be delayed without delaying the entire project.
(Short Answer)
4.8/5
(81)
A project manager should stop crashing a project if the time budget has been met or if the crash costs have exceeded the savings in indirect and penalty costs.
(True/False)
4.9/5
(82)
A project is an interrelated set of activities that has a definite starting and ending point.
(True/False)
4.8/5
(69)
Figure 7.2
-Which one of the following conditions violates the assumptions of PERT/CPM networks?
(Multiple Choice)
4.8/5
(80)
A project organization structure where team members are assigned to the project and work exclusively for the project manager is called:
(Multiple Choice)
4.8/5
(90)
A project tracking system should collect information on three topics for the project manager. What are these topics, why are they important, and what actions can the manager take to address any concerns that surface?
(Essay)
4.9/5
(81)
If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?
(Multiple Choice)
4.9/5
(75)
Table 7.9
-Using Table 7.9, what is the minimum time schedule for this project?
(Multiple Choice)
4.8/5
(70)
To obtain the latest start and latest finish time in a network diagram, we must work forward through the network.
(True/False)
4.9/5
(92)
Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time.

(Essay)
5.0/5
(83)
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks).
-Using Table 7.14, what is the probability that the project will take 16 or more weeks to complete?
(Multiple Choice)
4.8/5
(65)
Projects, and the application of project management, facilitate the implementation of operations strategy.
(True/False)
4.8/5
(68)
Assuming a beta distribution is being used, if the most pessimistic time for an activity increases by six weeks, what will happen to the expected time for that activity?
(Multiple Choice)
4.9/5
(87)
Table 7.2
-Using Table 7.2, which activity will have the largest amount of slack?
(Multiple Choice)
4.7/5
(71)